Works currently on programme. As of 5th January:
Block 1 - New roof complete. Groundworks and new drainage now in progress along with laying new slabs in drying area.
Block 2 - New roof complete and scaffold nearly dropped. New drainage/groundworks ongoing.
Block 3 - Roof tiling underway, approx. 50% complete. New cut roof fitted over the original flat roof.
Block 4 - New insulation complete. Extension work has started to roof and windows. OSB boarding for new pitched roof conversion.
Other - Preparation work has started on interior decorating in all 4 blocks and wiring ready for new communal doors to be fitted is underway.
Additional Works
Project progress:
Progressing as programmed, due to complete December 2023.
Completed social value initiatives:
- Pre-employment training and work experience - both provided at Tyler Court for one individual who worked with the CLO throughout November. Seven pre-employment training courses delivered in Birmingham on 21st November
- Apprenticeships and job starts - two apprenticeship opportunities and one job start at Birmingham
- Specialise qualification sponsorship - £163.96
- Financial contribution towards digital devices - £500
- Clarion Futures donation - £400
- Contractor engagement - One Meet the Contractor event at Tyler Court
- Provision of equipment or services - £50
Planned social value initiatives:
- Apprenticeship & job starts: Will be difficult to achieve in this within our current contract but we are actively sharing employment opportunities for job starts with Clarion on a monthly basis. Two apprentice positions and one CLO job start potentially awaiting interview confirmation
- Accredited Training: Target achieved
- Sponsorships & donations: Target achieved
- Employment, Training & Work Experience: Target achieved
- Digital Training: Awaiting Clarion approval
- Refurbishment projects: £500 allocated towards projects. Awaiting confirmation to allocate to either hanging baskets or signage for the community centre
- Contractor engagement: Target achieved, plus Christmas engagement event planned with donations of gifts for Tyler Court residents
- School engagement: Target achieved
- Staff volunteering: Finance team offered online training at community centre, awaiting Clarion approval