Works update - July 2023
Welcome to your works update for July, the information below provides an update on the works currently being delivered at Seaton Point.
Progress is continuing to the South-East corner of the Winter Gardens, 90% of the North-West corner is now fully completed.
The hoist has been adapted to reach the roof and access is now granted for the removal of the roof covering which started week commencing 7th August.
Delivery of the new roof covering has been achieved and the red fin on the roof has been fire proofed and received its new render system and paintwork in a lovely Terracotta Red.
The tank housing has received minor concrete repairs and we have applied a base coat. We are now applying two full coats of SIKA white top coat.
We have a 40yrd skip in the rear car park ready for the old roof covering to be cleared from the newly adapted hoist. Residents are advised to take advantage of the large skips which are easily available to clear any unwated items prior to us carrying out works to the winter gardens.
We are planning to open tier 3 of the South-West corner week commencing 14th August.
If you have any queries or concerns about the works being undertaken by Equans, please call your RLOs.