Resident Meeting Minutes_Jun23

08 Jun 2023

Thank you to everyone that attended our latest resident meeting, we've included a summary of the minutes below - you can also view the minutes by clicking here or visiting our 'Document Library'.


Thanks to everyone that has joined, and due to the number of residents present, we believe it's not a lot due to others being satisfied with the information we are providing.

The side of the building, we also need to install scaffold to carry out the work safely.

  • Trevon will contact you for boiler isolations
  • Cladding is being stripped, materials have been ordered and we are on track
  • Carrying out surveys and extra works on the roof. Replacement of doors etc.
  • Gas isolation works in progress, and we are on target
  • As we get closer to summer, we are looking to organise a social value event. We would like to organise a day in construction for kids around the area and within the blocks to have a chance to know and see what a day in construction is like.

Q&As

Q: When will the balcony be done?
Now, we are stripping the facade so once this is done. We are moving towards the balconies and once we are at that stage. RLO, Trevon will inform you in the next 2 weeks.

Q: Will we see what the decking looks like?
Yes, samples are going to be on site available and the RLO, Trevon will inform residents so they can view it.

Q: Would the residents get an ews1 form post works?
Ews1 form will be issued to the landlord, which is Southern Housing. Any residents who want it once it is issued to Southern Housing can request it.

Q: When will the work be completed?
September and we are still very much on track with it.