Works update - August 2024
Welcome to your resident's update from Equans. This is a great way for us to keep you up to date with all the work that has been going on so far and what we expect to achieve going forward.
If you have any queries about the works being undertaken by Equans, please direct your query to your appointed Resident Liaison Officer, Carole Coleman by calling 07880 786 442.
As you will be aware, Equans has been appointed by Southern Housing to replace cladding and associated fire remediation works at Whytecliffe Road South.
Our progress so far:
- We have commenced and are continuing with the installation of the cladding, including gas isolations to all levels and elevations
- The brickworks side rise cavity fire barrier works, to all windows, doors and slab installations on all levels will be starting from the roof level 6th floor downwards
- The brickwork balconies and floor slabs on the rear elevation commenced on 13th August
- The under-croft area is to start from 15th August. We will be carrying out the first fix on the scaffold areas on either side of the entrance ramp
Next month's key steps:
- We will be continuing with the new cladding works, gas isolations and brickworks to all elevations
- We will be commencing with the installation of the aluminium decking on the balconies
- We will be painting the balcony handrails and railings
Resident Evening Meeting
We will be holding our next resident meeting via TEAMS on Thursday 5th September from 6pm. You are all invited and an email invitation will go out to you closer to the time - we look forward to seeing you.
This update has been extracted from the August Resident Newsletter which can be viewed in full by clicking here.