Project Update - November 2019

Good progress has been made in the period with our first timber frame units being erected and the CFA piling works nearing completion.

The ground floor slabs to Phase 1 are now complete and we will continue with the erection of scaffold and timber frame to this area.

We are well underway with the drainage and ground floor slabs to Phase 2 and are planning the next tarmac visit for the end of November which will give us a clean site coming into the harder winter months.