Project Update - April 2021

We are happy to announce that good progress has been made in the past month with the successful hand over of 18 properties which residents are now starting to move into.

An additional 20 properties are due to be completed by the end of April 2021.

We have now completed all the off site road works to both Cooks Lane and King Street.

We continue to progress well with the erection of timber frames for houses that are due to be handed over at the end of the year.