Welcome to the latest update from the scheme's primary subcontractor, Oliver Connell & Son.
Once complete in Summer 2024, this exciting redevelopment will provide a 15-storey halls of residence. Features of this scheme include:
- A new gym
- External courtyards
- Roof terraces
- Shared kitchens
- Cinema room
- Laundry room
- Amenity space
- Staff offices
Progress on site: Site completed the reduced level dig and came across a lot of concrete obstructions that had to be removed. Site conducted a UXO survey and probed 95 locations to check for unexploded ordnances and nothing was found. The installation of the piling mat is 90% complete and piling works have commenced.
What's happening next? Site will be piling for the next nine weeks. Oliver Connell will be in attendance to assist the piling process and to manage works on site.
Local procurement and jobs
The Council, Oliver Connell and our main contractor, EQUANS (previously known as ENGIE), are committed to providing local employment, training and procurement opportunities.
Site will be supporting local businesses such as local supermarkets, restaurants, cafes and suppliers as much as possible whilst they complete the project.
If you are interested in working on site, local supply chain opportunities or finding out more information about the Employment and Training Strategy for Glengall Road please contact Trevor Walsh, Contracts Manager, Oliver Connell & Son Ltd on 07483034261 or at twalsh@oliverconnell.com
Oliver Connell & Son will be issuing a community newsletter each month to provide a regular update on the development. You can view a copy of each newsletter by visiting the document library - click here to view the newsletter for April.