August update from Oliver Connell

Welcome to the latest update from the scheme's primary subcontractor, Oliver Connell & Son.

Progress on site:
The first two cranes have been erected. The capping beam construction continues along the west elevation, its final section. On site we have begun the main dig inside the basement to reduce the ground level to basement slab level. 5,270 tonnes of soil, stone and sand have been dug and removed off site in the month of August. The construction of pile caps in the basement began towards the later end of the month. In August, site has poured 520 cubic metres of concrete along with installing 125 tonnes of rebar.

What's happening next?
Material within the basement will continue to be removed until all excess soil is gone. The basement foundations works will progress while beginning the waterproofing stage. The basement slab works will begin followed by the construction of vertical elements around the perimeter of the basement. The second crane will be erected mid September.


Local procurement and jobs

The Council, Oliver Connell and our main contractor, Equans are committed to providing local employment, training and procurement opportunities.

Site will be supporting local businesses such as local supermarkets, restaurants, cafes and suppliers as much as possible whilst they complete the project.

If you are interested in working on site, local supply chain opportunities or finding out more information about the Employment and Training Strategy for Glengall Road please contact Trevor Walsh, Contracts Manager, Oliver Connell & Son Ltd on 07483034261 or at twalsh@oliverconnell.com


Oliver Connell & Son will be issuing a community newsletter each month to provide a regular update on the development. You can view a copy of each newsletter by visiting the document library - click here to view the newsletter for August.