July update from Oliver Connell

Welcome to the latest update from the scheme's primary subcontractor, Oliver Connell & Son.

Progress on site:
Piling has been completed with a total of 511 piles constructed. The capping beam construction continues along the Bianca Road elevation. On site we have begun the main body of foundation works which comprises of large 2.2m high beams spanning a distance of 9m, these beams span across a large services tunnel deep underground. The crane base for TC1 has been cast, once the required concrete strength is reached the crane can be safely erected.

What's happening next?
The planned erection date for the first tower crane on site will be 4th of August. With the crane erected the works on site can begin to work more fluidly and are not constrained to as many movement limitations. Works will progress along the capping beam along the Bianca Road elevation and the large ground beams will continue working from East to West toward Glengall Road.


Local procurement and jobs

The Council, Oliver Connell and our main contractor, EQUANS (previously known as ENGIE), are committed to providing local employment, training and procurement opportunities.

Site will be supporting local businesses such as local supermarkets, restaurants, cafes and suppliers as much as possible whilst they complete the project.

If you are interested in working on site, local supply chain opportunities or finding out more information about the Employment and Training Strategy for Glengall Road please contact Trevor Walsh, Contracts Manager, Oliver Connell & Son Ltd on 07483034261 or at twalsh@oliverconnell.com


Oliver Connell & Son will be issuing a community newsletter each month to provide a regular update on the development. You can view a copy of each newsletter by visiting the document library - click here to view the newsletter for July.