July works update
We're delighted to provide our July update on the works being delivered at Glengall Road. If you have any queries or concerns about the works being undertaken by Equans please call Tony Doyle on 07879 433 118.
Works are progressing well on site with FP McCann now having completed the cladding panels to the lower and upper ground floor insitu frame. We have now commenced with the offsite manufactured first floor structural insulated panels which arrive to site fully finished, with brick cladding complete, coloured concrete, windows, even down to the ventilation grilles.
We are rapidly installing first floor internal walls, stair cores and now have the first of the second floor slabs in place.
West elevation cladding continuing. Installing spandrel panels across the 1st and 2nd floors | Cladding complete on the South elevation across the lower and upper ground floors | 2nd floor slabs being offloaded awaiting installation into position |
Cladding complete on the South elevation across the lower and upper ground floors |
1st floor insulated panels complete on the North elevation | South and East cladding complete |