September update from Oliver Connell
Welcome to the latest update from the scheme's primary subcontractor, Oliver Connell & Son.
Progress on site:
Our second crane was erected during the beginning of September. This will increase speed and mobility of materials across the entirety of the site and most importantly increasing our access to vertical elements. Continuing with the basement reduced dig there has been an additional 2,430 tonnes of soil and stone removed. 630m2 of concrete has been poured into foundation pile caps, beams and the first slab pour in the basement.
What's happening next?
With the first section of the basement slab poured the first vertical elements of the buildings substructure can begin to be cast. Starting with the basement liner walls around the perimeter of the basement. Then progressing onto core walls and columns which will span from the substructure to roof in varying locations. With an adequate area of columns and core walls cast and cured to the required design strength the next level of slab can then begin to be constructed using falsework props to carrying the load at the necessary height and formwork shutters to create the shape.
Local procurement and jobs
The Council, Oliver Connell and our main contractor, Equans, are committed to providing local employment, training and procurement opportunities.
Site will be supporting local businesses such as local supermarkets, restaurants, cafes and suppliers as much as possible whilst they complete the project.
If you are interested in working on site, local supply chain opportunities or finding out more information about the Employment and Training Strategy for Glengall Road please contact Trevor Walsh, Contracts Manager, Oliver Connell & Son Ltd on 07483034261 or at twalsh@oliverconnell.com
Oliver Connell & Son will be issuing a community newsletter each month to provide a regular update on the development. You can view a copy of each newsletter by visiting the document library - click here to view the newsletter for September.