Works update - August 2024
Welcome to your works update for August, the information below provides an update on the works currently being delivered at Seaton Point.
We have been progressively striking the scaffold out and we are now down to level 16 on three elevations of the building. We can also confirm that we have installed the last bedroom window within the block so all kitchen and bathroom windows have now been fully installed in all properties.
Our team are currently working on installing the EWI around the winter gardens and continuing to render where possible across the block.
We have also released the ties for our passenger hoist which over the next month, residents will see our team striking out the elevations on the north side of the block.
If you would like a further update or have any queries or concerns about the works being undertaken by Equans, please call your RLOs.