Works update - November 2023
Welcome to your works update for November, the information below provides an update on the works currently being delivered at Seaton Point.
- Winter garden progress to SW corner, started on floor 19 and opened to floor 15 before end of the year
- Lower floor levels to complete to the SE corner and floor 1 on the NW corner
- Two new roofs installed to the 21st floor winter gardens to the NW and SE corners
- Roof replacement 80% complete, upstands and parapet wall details to complete
- Now received access to the flat refusing access so now progress can start on the NE corner. Further blockage below will be issuing access in the next week with one final access to be made within two weeks, then we can start to progress with rendering from the 21st floor down, achieve pigeon control and start to remove scaffolding mid next year - all going well
From all the team at Seaton Point, we wish you all a Merry Christmas and a Happy New Year.