Works update - September 2024

Welcome to your works update for September, the information below provides an update on the works currently being delivered at Seaton Point.

We are making great progress with the topcoat and the removal of scaffold to the east, south and west elevations and we are currently striking the scaffolding at level 13.

We have also recently signed off level 20 on the north elevation and the scaffolding has been removed.

The team are currently working the topcoat to level 19 and we look to have this handed over by 14th October. Once the scaffold is fully struck down to level 13 the team will then make a start on patching in the scaffold tie holes and once completed we will then be able to start the next topcoat process and cleaning of these levels.

All in all, great progress being made.


If you would like a further update or have any queries or concerns about the works being undertaken by Equans, please call your RLOs.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>