Hallam Court and Olivia Court


Welcome to the microsite for Hallam Court and Olivia Court. This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Equans is undertaking emergency works to balconies including the replacement of combustible materials. Designs are also being prepared for all other works at Hallam Court and Olivia Court.


Equans is carrying out works to your building.

However, you’ll need to contact your landlord, Southern Housing,
if you’ve questions which are not related to the works being
carried out.

There are a number of ways you can get in touch with them: www.southernhousing.org.uk/contact-us








Welcome to the microsite for Hallam Court and Olivia Court. This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Equans is undertaking emergency works to balconies including the replacement of combustible materials. Designs are also being prepared for all other works at Hallam Court and Olivia Court.


Equans is carrying out works to your building.

However, you’ll need to contact your landlord, Southern Housing,
if you’ve questions which are not related to the works being
carried out.

There are a number of ways you can get in touch with them: www.southernhousing.org.uk/contact-us







  • Resident Meeting Minutes - 31st January

    We are pleased to share the minutes from our last resident meeting for Hallam Court residents held on 31st January.

    As a reminder, if you have any queries, questions or concerns regarding the works being undertaken by Equans please direct them to your appointed Resident Liaison Officer, Michael Olaadedini.


    Questions asked during the meeting:

    Q: What is monoflex?

    A: Monoflex is a protective sheet which is weather and fire resistant. Installed to protect the building while the work is ongoing.

    Q: What is Y wall?

    A: Y wall is a sheeting board used on timber frame structures. It is used behind the facade and is non-combustible.

    Q: Is the respite now active?

    A: Yes, this can be booked through the RLO, Michael.

    Q: What is the time scale for this project?

    A: Looking at the programme we anticipate a completion date of May 2024.

    Q: What is OSB?

    A: OSB stands for Oriented Strand Board which is a type of engineered wood like particle board, formed by adding adhesives and then compressing layers of wood strands in specific orientations.

    Q: When are you going to install the balcony balustrade?

    A: The installation of the balustrade is anticipated to be completed towards the end of the project. We are making every effort to ensure that this installation aligns with the project timeline and meets all necessary requirements.

    Q: Will the block achieve a satisfactory EWS1?

    A: The block will receive a satisfactory EWS1 and design consultation can be shared with lenders.

  • Olivia Court Works Update - December 2023

    Welcome to your latest works update - this is where we will regularly update you on our progress with the works being undertaken at Olivia Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to the residents at Olivia Court as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of near your flat.

    Our progress to date:

    • Scaffold erection has been completed
    • Ongoing balcony light removal
    • Respite unit completed

    Important information:

    Windows: We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The make of the insulation to the rear is EPS which is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk: We would also like to remind residents not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Christmas news update: Hallam Court Festive Celebrations:

    During December Michael gave out the Christmas raffle draw basket hamper to local residents. We would like to thank all the residents for their continued support and co-operation. Your dedication to our community is greatly appreciated and does not go unnoticed. Together, we have achieved so much, and we look forward to continuing to work alongside each and every one of you to make our community an even better place to live. Your involvement is crucial, and we are truly grateful for your ongoing commitment. Thank you for being such valuable members of our community.



    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

  • Hallam Court Works Update - December 2023

    Welcome to your latest works update - this is where we will regularly update you on our progress with the works being undertaken at Hallam Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to the residents at Hallam Court as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of near your flat.

    Our progress to date:

    • Scaffold erection has been completed
    • Stripping of existing external cladding completed
    • Works to flats affected by fire completed

    Important information:

    Windows: We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The make of the insulation to the rear is EPS which is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk: We would also like to remind residents not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Unauthorised access: Please note that only Equans employees and their representatives are permitted access to scaffolding. For their own safety, no other persons are allowed to climb onto the scaffold under any circumstances - this applies particularly to children! Any authorised persons accessing the scaffold outside of our normal working hours (Monday to Friday, 8am-5pm) should be immediately reported to the Police.

    Christmas news update: Hallam Court Festive Celebrations:

    During December Michael gave out the Christmas raffle draw basket hamper to local residents. We would like to thank all the residents for their continued support and co-operation. Your dedication to our community is greatly appreciated and does not go unnoticed. Together, we have achieved so much, and we look forward to continuing to work alongside each and every one of you to make our community an even better place to live. Your involvement is crucial, and we are truly grateful for your ongoing commitment. Thank you for being such valuable members of our community.



    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

  • Equans spread festive cheer with hamper and selection box donations

    To help spread some festive cheer this Christmas, members of the Equans site team including Resident Liaison Officer, Michael surprised a number of residents with a Christmas themed hamper and selection boxes for children.

    The lucky residents were chosen at random and on 20th December they received a surprise visit from Michael with their amazing hamper prize full to the brim with a variety of festive treats and goodies.

    This goodwill gesture was part of a larger initiative carried out across our various Southern Housing schemes, organised by Equans' in-house Social Value team.


    Please click here to watch a short video capturing the event.

  • Collect your free Christmas selection box

    Available from Tuesday 19th to Thursday 21st December, local residents can collect a free Christmas selection box from Equans.

    This year Equans are spreading festive cheer by handing out free Christmas selection boxes to Southern Housing residents at Hallam Court and Olivia Court.

    Please visit our site office or get in touch with your RLO, Michael to collect your free box.

  • We're closing for the festive holiday!

    We would like to inform you that our Hallam Court & Olivia Court site will be shutting for the festive holiday from Friday 22nd December and re-opening on Tuesday 2nd January 2024.

    In the event of an emergency during this period, please continue to use our dedicated out of hours number - 07785 312 158.

    From everyone in the Hallam Court & Olivia Court site team, we hope you enjoy the festive break.


  • Olivia Court Works Update - 16th November 2023

    Welcome to your latest works update - this is where we will regularly update you on our progress with the works being undertaken at Olivia Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to the residents at Olivia Court as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of near your flat.

    Our progress to date:

    • Respite unit has been completed
    • Front scaffold elevation has been completed
    • Resident property profile has been completed

    Over the next month:

    • Decking installations still ongoing

    Important information:

    Windows: We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The make of the insulation to the rear is EPS which is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk: We would also like to remind residents not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Unauthorised access: Please note that only Equans employees and their representatives are permitted access to scaffolding. For their own safety, no other persons are allowed to climb onto the scaffold under any circumstances - this applies particularly to children! Any authorised persons accessing the scaffold outside of our normal working hours (Monday to Friday, 8am-5pm) should be immediately reported to the Police.

    Residents Meeting: We are pleased to invite you to the upcoming Residents Meeting, which will take place via Microsoft Teams on November 29th from 6.30pm - 7pm. This virtual meeting aims to provide updates on community matters, address concerns, and foster open communication among residents. To join the Microsoft teams meeting please enter the meeting ID: 328 627 605 432 and the passcode: ptmJVJ

    Minutes from the last resident meeting held on 25th October:

    Q1: When is the completion of this ongoing project?
    We are currently still in the design stage and expect this to be reviewed by week commencing 6th November

    Q2: Residents said, she has a concrete slab on her balcony. She asked, are they going to change her balcony too?
    No, as concrete is generally considered to be a fire-resistant material due to its non-combustible nature.

    Additionally, the residents also enquired about the present stage that we are now on this project.
    We are due to have structural information and report complete by November. Once we have this, we can produce a programme to include a start date and anticipated completion dates.

    Christmas news update: Hallam Court, Get Ready for Festive Celebrations:

    We are excited to announce that the annual Christmas draw for the residents of Olivia Court is on its way, along with special gift bags for the children in our community. Additionally, we are pleased to inform you that a local food bank charity has been chosen, and we are organising a food donation drive to support our neighbours in need.


    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

  • Hallam Court Works Update - 16th November 2023

    Welcome to your latest works update where we regularly update you on our progress with the works being undertaken at Hallam Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to residents as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of your flat or near your flat.

    Our progress to date:

    • Completion of scaffold to the rear of the block
    • Completion of the front balcony decking and the rear balcony decking
    • Ongoing side elevation at Strathmore Road

    Windows - We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The debris from all of the works is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk - We would like to remind everyone not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Residents Meeting: The residents meeting previously scheduled for the 29th November 2023 has now been re-scheduled for the 6th December from 6-7pm. We apologise for any inconvenience this may cause and appreciate your understanding. This meeting will provide an opportunity for us to discuss important matters and address any concerns or suggestions you may have.

    Details to join the Microsoft Teams meeting:
    ID: 385 420 130 563
    Passcode: 9NiX5X

    Minutes from the last resident meeting held on 25th October:

    Q1: When is the completion of this ongoing project?
    We are currently still in the design stage and expect this to be reviewed by week commencing 6th November

    Q2: Residents said, she has a concrete slab on her balcony. She asked, are they going to change her balcony too?
    No, as concrete is generally considered to be a fire-resistant material due to its non-combustible nature.

    Additionally, the residents also enquired about the present stage that we are now on this project.
    We are due to have structural information and report complete by November. Once we have this, we can produce a programme to include a start date and anticipated completion dates.

    Christmas news update: Hallam Court, Get Ready for Festive Celebrations:

    We are excited to announce that the annual Christmas draw for the residents of Hallam Court is on its way, along with special gift bags for the children in our community. Additionally, we are pleased to inform you that a local food bank charity has been chosen, and we are organising a food donation drive to support our neighbours in need.


    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

  • Olivia Court Works Update - 1st November 2023

    Welcome to your latest works update - this is where we will regularly update you on our progress with the works being undertaken at Olivia Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to the residents at Olivia Court as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of near your flat.

    Our progress to date:

    • Respite unit has been completed
    • Front scaffold elevation has been completed
    • Resident property profile has been completed

    Over the next month:

    • Decking installations are ongoing

    Important information:

    Windows: We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The make of the insulation to the rear is EPS which is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk: We would also like to remind residents not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Unauthorised access: Please note that only Equans employees and their representatives are permitted access to scaffolding. For their own safety, no other persons are allowed to climb onto the scaffold under any circumstances - this applies particularly to children! Any authorised persons accessing the scaffold outside of our normal working hours (Monday to Friday, 8am-5pm) should be immediately reported to the Police.

    Residents Meeting: Our next resident's meeting will be held via Microsoft Teams on Wednesday 29th November from 6.30pm. Instructions on how to join this meeting will be included within our next newsletter. This meeting will provide an opportunity for us to discuss important matters and address any concerns or suggestions you may have.

    Minutes from the last resident meeting held on 25th October:

    Q1: When is the completion of this ongoing project?
    We are currently still in the design stage and expect this to be reviewed by week commencing 6th November

    Q2: Residents said, she has a concrete slab on her balcony. She asked, are they going to change her balcony too?
    No, as concrete is generally considered to be a fire-resistant material due to its non-combustible nature.

    Additionally, the residents also enquired about the present stage that we are now on this project.
    We are due to have structural information and report complete by November. Once we have this, we can produce a programme to include a start date and anticipated completion dates.


    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

  • Hallam Court Works Update - 1st November 2023

    Welcome to your latest works update where we regularly update you on our progress with the works being undertaken at Hallam Court.

    If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael Olaadedini on 07402 861 522.


    It is our intention to provide a regular update to residents as to what works have taken place and what works are upcoming. In between these updates the site team will be contacting you to make appointments for any surveys or works that need to be done to the outside of your flat or near your flat.

    Our progress to date:

    • Completion of scaffold to the rear of the block
    • Completion of the front balcony decking and the rear balcony decking
    • Works to carry out intrusive investigations to reveal timber framing on 7th November
    • Scaffold to the side elevation (Stratmore Road) still ongoing

    Windows - We would like to remind everyone to keep their windows closed (due to potential but not anticipated noise/debris/dust etc.) as well as the privacy element. The debris from all of the works is very light and can easily be blown back into your property.

    Scaffold Health & Safety Risk - We would like to remind everyone not to smoke on their balconies and throw cigarette butts on the scaffold along with other items such as rubbish, toys etc. Unfortunately, cigarettes and cigarette butts can easily be blown back into the building and/or onto the scaffold or existing cladding and cause a fire.

    Residents Meeting: Our next resident's meeting will be held via Microsoft Teams on Wednesday 29th November from 6pm-6.30pm. Instructions on how to join the meeting will be included in our next newsletter. This meeting will provide an opportunity for us to discuss important matters and address any concerns or suggestions you may have.

    Minutes from the last resident meeting held on 25th October:

    Q1: When is the completion of this ongoing project?
    We are currently still in the design stage and expect this to be reviewed by week commencing 6th November

    Q2: Residents said, she has a concrete slab on her balcony. She asked, are they going to change her balcony too?
    No, as concrete is generally considered to be a fire-resistant material due to its non-combustible nature.

    Additionally, the residents also enquired about the present stage that we are now on this project.
    We are due to have structural information and report complete by November. Once we have this, we can produce a programme to include a start date and anticipated completion dates.


    The information above has been taken from our latest Resident Newsletter which can be viewed in full by clicking here.

Page last updated: 13 Mar 2025, 08:32 AM