An update on our works - August 2024

Welcome to our latest works update for Iveagh House.

These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.


It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.

Our progress throughout August:

  • We are currently waiting on designs and the planning application
  • New pipework supplying the annex has been installed and is to be boxed in with bulk head ceiling once the new laterals have been run to the RHS
  • All the new boilers have now been installed including the boiler flue. A smoke test has also been completed. The new heating control panel has been installed
  • Front and rear balcony works are on hold due to planning
  • Repairs to the window surround is now completed as well as the heating system
  • Remedial works to the Juliet balconies are complete including installation of the new steel packers. We are currently applying mastic sealant and the second coat

Works due to commence in September:

  • Kitchen replacement works have recently been instructed and Howdens will be on site soon to carry out designs
  • Sprinkler system, new lateral mains, bathrooms fans and fire stopping works are all currently on hold