An update on our works - February 2024
Welcome to our latest works update for Iveagh House.
These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.
It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.
Our progress throughout February:
- Works have started on the annexe building roof replacement and are currently 75% complete
- Works are ongoing to the new veranda balconies
- Window concrete surrounds on the annexe building are ongoing
- Automatic opening vents (AOVs) to north, centre and south stairwells are ongoing
- Communal electrical works are ongoing
- Communal fire detection system are ongoing
- We are approximately 90-95% complete on the concrete and brickwork repairs
- We are approximately 85% complete on the balconies (full size and juliet's)
- All HIU cupboards on all floors have been built however decorative works to the corridors will be done separately
Important information:
The Equans RLO, Ayo and Guinness Customer Liaison Officer are available at the Community Hall, Monday to Friday during the following hours: 8am-12pm and 2pm-5pm. They are available to visit and have face-to-face conversations.