Our progress to date:

Throughout January we started the following works:

  • Installation of new juliet balconies
  • External brickwork/concrete repairs to the main block and the annex
  • External rendering
  • Internal remedial works to various properties
  • Installation of new HIU cupboards within communal areas
  • Internal heating renewal works
  • Installation of new kitchen fans

Upcoming works throughout February:

  • Installation of new balcony terrace floor coverings
  • Installation of AOVs (Automatic Opening Vents) to communal areas
  • Installation of new roof coverings to the annex

Important information: