An update on our works - July 2024
Welcome to our latest works update for Iveagh House.
These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.
It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.
Our progress throughout July:
- Decorations to the front elevation has now been completed and signed off
- All of the new boilers have now been installed - we have had to build a scaffold around the chimney/flue to pull through a plastic liner and connect to the new boilers
- The remainder of the roof works are on hold due to the chimney scaffold, once complete it will be struck and then we will complete the north veranda to the vapour barrier
- Front and rear balcony works are on hold due to planning
- Heating systems are being installed in the annex. No's 166 and 164 are already installed with No.162 due to be completed shortly
- Concrete repairs to the window surround at No.162 will commence on 19th August and should take approximately five days
- Remedial works to the Juliet balconies are ongoing including applying mastic sealant and applying a second coat
- Renovations to the new laundry room on the first floor has started
Works due to commence in August:
- Scaffolders to erect a small platform over the new boilers, to coincide with the flue liner installation, connect up the new flue and some pipework adaptations
- Sprinkler system, new lateral mains, bathrooms fans and fire stopping works are all currently on hold