An update on our works - June 2024
Welcome to our latest works update for Iveagh House.
These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.
It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.
Our progress throughout June:
- All Automatic Opening Vents (AOVs) have been installed
- Roofs are complete, except veranda balconies
- Concrete repairs and external painting is ongoing
- Works to veranda balconies ongoing
- Plantroom and heating works ongoing
Works due to commence in July:
- Re-lining of the buildings' main flue and plumbing works to annex