External works update

Please see details below included from a letter sent to residents regarding the external works.


Equans are carrying out refurbishing works in Iveagh House on behalf of The Guinness Partnership. At this stage, we are carrying out works which include the following:

  • Plant room works in the basement: It will start on Monday 1st July and take approximately two weeks to complete. During this period, the northside staircase area will be blocked but you will still have access to the central and southside staircases
  • 6th floor balcony works: Removing of the concrete screed on the flooring and laying new membrane. This work commenced on Monday 24th June and will take approximately three weeks to complete

Please note that there will be noise during both of these works, but we'll ensure that the grinding and drilling tasks involved are completed between 10am and 2pm, Monday to Friday.

We apologise for any disruption this work may cause. We will keep this to a minimum and ensure that all health and safety procedures are in place.

If you have any queries or concerns regarding our work, please contact Ayo Adagunodo on 07890 630 331 or via email at ayo.adagunodo@equans.com.