New Progress Photos - March 2025

We've uploaded five new photos to demonstrate how works are progressing.

Our progress of works currently consists of:

Installing rainwater pipes and kitchen waste piped externally

6th floor electrical lateral mains installations in communal areas.

New scope of works in apartments which are voids and decanted. They include the following:

  • Drilling cores and installing plenums for new bathroom extractor fans
  • Bathroom extractor fan installations, including the encasement of the ducting.
  • Sprinkler installations including the encasement.
  • Smoke alarm installations in the flats
  • Completing outstanding works in flats. These scope of work include kitchen extractor fans and electrical literal mains installations
  • Fire safety works to the loft including installing fire safety boards
  • 6th floor balcony and terrace floor lang tiles completed and the railing installations will be commencing soon.

Subcontractors contracted by Guinness are currently carrying out the following:

  • Access control and CCTV installations – enabling and communal works
  • Kitchen and bathroom refurbishments in void properties
  • Void flats refurbishments including decorations and flooring renewals

Take a look a the photos by clicking on the Photo Gallery icon above