Resident Update - 30th August 2024

Welcome to your weekly update from Equans. This is a great way for us to keep you up to date with all the work that has been going on so far and what we expect to achieve going forward.

If you have any queries about the works being undertaken by Equans, please direct your query to your appointed Resident Liaison Officer, Alena Webster by calling 07977 834 553.


As you will be aware, Equans has been appointed by Southern Housing to undertake regeneration works to the external cladding at Mill Court.

As of 29th August we have been here for 12 weeks and here's what's happened so far:

Works update:

  • Scaffolding is now completed. We will be starting to remove the cladding
  • A skip has now been placed at the front of the building, and all rubbish has been cleared from the back garden
  • The hoist has been installed and scaffold has been handed over
  • All blue netting around the scaffold has been installed

Next week:

  • If you have not had the full pre-condition survey, then please call Alena urgently on 07977 834 553 to arrange to have yours carried out. These need to be completed by next week otherwise we will be held up, which in turn will hold up the programme leading to delays
  • Cladding will be removed where we have pre-condition surveys
  • On Monday 2nd September there will be a coffee afternoon at 1pm in the summerhouse if anyone would like to attend
  • We have consultants on site on 11th September to examine the building

If anyone needs any more information, please contact Alena or attend the regular coffee afternoons.


Please click here to view the Resident Update in full.