Kingfisher Court Resident Newsletter - July 2024
Welcome to our latest works update for our progress with the works being undertaken at Kingfisher Court.
These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Michael on 07402 861 522.
Welcome to your July newsletter - this is a way for us to keep you up date with all the work that has been going on so far and what we expect to achieve going forward.
Our progress to date:
The cladding contractor has completed 90% of the deconstruction works. Preparation work has commenced to install additional studs and Y wall board.
Security reminder:
Regarding the issue with trespassers, we have added additional fencing to help prevent access to the scaffold from the alleyway. We have a security alarm that is set every evening. Please remain vigilant if any trespassers are seen on the scaffold please call the Police immediately.
Further information:
Movement in properties due to works: Any movement or new damage noticed in your property should be reported to the site team. This will be recorded to be completed at the end of the project.
We would still like your ideas for post-project on ways to renew the back garden area. For example, garden gnomes, birdfeeders etc.
Monthly resident's meeting:
We would like to invite you all to the next resident's meeting on Wednesday 24th July.
The meeting will take place from 6.30-7.30pm via Microsoft Teams - a link will be sent out.
During the meeting, there will be an opportunity to provide your views, concerns and to ask questions. Representatives from both Equans and Southern Housing will be present.
We look forward to meeting you all.
Please click here to view the July newsletter in full.