Resident newsletter - September 2024

Welcome to your first works update - this is where we will regularly update you on our progress with the works being undertaken at Parkside - Market Estate.

These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO).


Meet your site team

The team from Equans responsible for the works at 5-7 Mackintosh Lane are:

  • Resident Liaison Officer: Sanusi Conteh
  • Site Manager: Raymond Mills
  • Contracts Manager: Mick Bull

Further details including phone numbers and email addresses can be viewed within our 'Your site team' section on the homepage or by clicking here.

Our progress to date:

  • We have commenced the stripping of panels to selected areas on 2-50 New Clocktower Place for inspection/survey/design purposes to establish the full extent of works required
  • A scaffold tower has also been erected to Chris Pullen Way (2-42) and stripping to selected areas for inspection/survey/design commenced 12th September
  • We are currently awaiting pavement, scaffold and parking suspension licences from Islington Council in order to proceed with the next scaffold tower to Drovers Way (1-21) and Chris Pullen Way (1-41). When we are in possession of this, we will update residents with scaffold information and dates

Reminders:

We understand that our works are impacting on the residents, and we are trying our best to reduce the inconvenience caused. Please bear with us.

We are appealing to all residents to refrain from organising barbecues on their balcony, throwing cigarette butts, bottles and sharps which have the potential of inflicting harm and a health hazard.


Please click here to view the September newsletter in full.