Welcome to the microsite for the Silchester Estate. Equans is undertaking works on behalf of the Royal Borough of Kensington & Chelsea.

This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

The works on this scheme include the refurbishment of and remedial works to four 20-storey tower blocks across the Silchester Estate, each containing a mix of one, two and three bedroom apartments, being Dixon House, Frinstead House, Markland House and Whitstable House. A full scope of works can be found within our Frequently Asked Questions (FAQs) section.

The main contract works are planned to start on site from 4th March 2024 with phased commencement for each block and phased completion as follows:

Markland House: Planned to start 4th March 2024 with an estimated completion of January 2025
Frinstead House: Planned to start July 2024 with an estimated completion of March 2025
Dixon House: Planned to start November 2024 with an estimated completion of July 2025
Whitstable House: Planned to start February 2025 with an estimated completion of October 2025. Lift works will be brought forward to start in May 2024

This website will keep everyone updated on the progress of the scheme - and if you have any questions, please refer to the contact us section.






Welcome to the microsite for the Silchester Estate. Equans is undertaking works on behalf of the Royal Borough of Kensington & Chelsea.

This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

The works on this scheme include the refurbishment of and remedial works to four 20-storey tower blocks across the Silchester Estate, each containing a mix of one, two and three bedroom apartments, being Dixon House, Frinstead House, Markland House and Whitstable House. A full scope of works can be found within our Frequently Asked Questions (FAQs) section.

The main contract works are planned to start on site from 4th March 2024 with phased commencement for each block and phased completion as follows:

Markland House: Planned to start 4th March 2024 with an estimated completion of January 2025
Frinstead House: Planned to start July 2024 with an estimated completion of March 2025
Dixon House: Planned to start November 2024 with an estimated completion of July 2025
Whitstable House: Planned to start February 2025 with an estimated completion of October 2025. Lift works will be brought forward to start in May 2024

This website will keep everyone updated on the progress of the scheme - and if you have any questions, please refer to the contact us section.





  • Happy Halloween from Equans

    From all of us at Equans, we wish you a happy Halloween.


    A children's activity pack can be collected from your Resident Liaison Officer. Alternatively this can be viewed and downloaded from our 'Documents Library'.

    Please be careful if carving pumpkins and stay safe whilst trick or treating.

Page last updated: 26 Feb 2025, 08:58 AM