Welcome to our site works update for June
June has seen the continuation of progress through the east and west wing areas.
Both MVHR (ventilation system) units have been installed in the east wing loft space, the process of installation was a challenge as they needed to be unpacked and re-assembled in the loft space. The progression of M&E works has been at full speed and has provided enablement of program sequence completions.
Carpentry works are in full swing in the west wing communal area with bookcases and shelving being crafted in the library.
As always, we apologise for any inconveniences arising from our works.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in July:
East wing:
- Completion of M&E services
- Closing of risers
- Closing of walls and ceilings
- Plastering to walls and ceilings
- Progression of loft space works
New lobby entrance:
- Installation of new central core steel works to lobby lift
North wing:
- Continued design related planning and surveys
West wing:
- Progression of ground floor west wing areas, and progression of garden/landscaping areas
If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.