Chelsea Court


Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.

As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.

We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.

The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.



Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.

As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.

We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.

The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.


  • Happy Halloween

    On behalf of the site team, Equans wish you a Happy Halloween.

    Don't forget, there's a children's Halloween activity pack available to download - click here or alternatively ask your RLO for a copy.


  • Works update - September 2024

    Welcome to our site works update for September

    August has seen the continuation of progress throughout the east and west wings and new entrance area.

    M&E works within the risers is now complete allowing closing and fire-proofing to take place. Final plastering within the flats is now fully underway along with preparation to install kitchens and bathrooms.

    The west wing ground floor communal area has been progressing well, both kitchens have been fitted along with carpentry and painting works.

    As always, we apologise for any inconveniences arising from our works.

    What to expect in October:

    East wing:

    • Commencement of kitchen and bathrooms
    • Closing of risers
    • Closing of walls and ceilings
    • Plastering to walls and ceilings
    • Paint works
    • Window remediations

    New lobby entrance:

    • Installation of new central core steel works to lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Progression of ground floor west wing areas, and progression of garden/landscaping areas
    • Progression of timber works to new entrance

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for September, please click here.

  • Works update - August 2024

    Welcome to our site works update for August

    August has seen the continuation of progress throughout the east wing, and new entrance area.

    Mechanical and electrical (M&E) works are now almost complete in risers making way for fireproofing to take place, fire dampers within the ceiling voids are near completion and plastering has started within flats enabling bathrooms and kitchens to progress.

    Work on the east wing 5th floor is also in full swing, plaster boarding to mansard timbers and MVHR connections are moving along nicely.

    As always, we apologies for any inconveniences arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in August:

    East wing:

    • Commencement of kitchen and bathrooms
    • Closing of risers
    • Closing of walls and ceilings
    • Plastering to walls and ceilings

    New lobby entrance:

    • Installation of new central core steel works to lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Progression of ground floor west wing areas, and progression of garden/landscaping areas
    • Progression of timber works to new entrance

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for August, please click here.

  • Works update - July 2024

    Welcome to our site works update for July

    July has seen the continuation of progress throughout the east and west wing areas.

    The progression of M&E works has continued at full speed allowing critical riser works to take place, fire dampers within the ceiling voids are now being installed.

    Brick and blockwork work in the new entrance area is near completion and the lower retaining wall is now completed.

    As always, we apologise for any inconveniences arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in August:

    East wing:

    • Completion of M&E services
    • Closing of risers
    • Closing of walls and ceilings
    • Plastering to walls and ceilings

    New lobby entrance:

    • Installation of new central core steel works to lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Progression of ground floor west wing areas, and progression of garden/landscaping areas
    • Progression of timber works to new entrance

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for July, please click here.

  • Works update - June 2024

    Welcome to our site works update for June

    June has seen the continuation of progress through the east and west wing areas.

    Both MVHR (ventilation system) units have been installed in the east wing loft space, the process of installation was a challenge as they needed to be unpacked and re-assembled in the loft space. The progression of M&E works has been at full speed and has provided enablement of program sequence completions.

    Carpentry works are in full swing in the west wing communal area with bookcases and shelving being crafted in the library.

    As always, we apologise for any inconveniences arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in July:

    East wing:

    • Completion of M&E services
    • Closing of risers
    • Closing of walls and ceilings
    • Plastering to walls and ceilings
    • Progression of loft space works

    New lobby entrance:

    • Installation of new central core steel works to lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Progression of ground floor west wing areas, and progression of garden/landscaping areas

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for June, please click here.

  • Works update - May 2024

    Welcome to our site works update for May

    May has seen the continuation of progress throughout the east and west wing areas. The MVHR (ventilation system) platform has now been installed, the new entrance steel work has been completed and the garden area has been prepped for progression of the works.

    You will still see workmen in the lift area on the staircase lobbies so please do take care when passing these areas until works have been completed. A banksman will always be in place to ensure your safety during these works.

    As always, we apologise for any inconvenience arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in May:

    East wing:

    • Completion of M&E services
    • Closing of risers
    • Closing of walls and ceilings

    New lobby entrance:

    • Installation of new central core lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Completion of ground floor west wing areas, and progression of garden/landscaping areas

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for May, please click here.

  • Works update - March/April 2024

    Welcome to our site works update for March/April

    April will see the continuation of progress throughout the east and west wing areas. The central core lobby lift has been removed and is being prepared for the installation of the new one. You will see workmen in the lift area on the staircase lobby's so please do take care when passing these areas, a banksman will always be in place to ensure your safety during these works.

    Structural surveys and investigations in the north wing are fully underway, with ceiling removals to obtain vital design information for the north wing refurbishment. The commencement of sprinkler works in the east wing has enabled more works to progress including completion aspects of M&E.

    We apologise for any inconveniences arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in May:

    East wing:

    • Completion of M&E installations to remaining risers, flats and ceilings

    New lobby entrance:

    • Installation of new central core lobby lift

    North wing:

    • Continued design related planning and surveys

    West wing:

    • Construction and installation of the new entrance lobby steel frame along with continued design related planning including the completion of ground floor west wing areas

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for March/April, please click here.

  • Site achieves National Considerate Constructors Scheme Award

    supporting image

    We are thrilled to announce that the Chelsea Court scheme has received a 2024 National CCS Award.

    This award is a real testament to the site team's approach and how they deliver the works, with a genuine commitment to having a positive impact in the communities where they operate.

    Regeneration Director for Equans, Barry McCarthy commented: "Visit after visit, the delivery team involved received excellent CCS scores (including four consecutive 45/45 results), setting and raising the bar in our industry for what considerate construction looks like - you should all be extremely proud to be recognised with this exceptional accolade. Well done and thank you."

    The CCS' national award scheme has been rewarding the UK’s most considerate sites since 1998 when they launched the National Site Awards. Today like then, the Awards are one of the most recognised construction industry awards in the sector and represent an exceptional accolade that recognises the sites that have made the greatest contribution towards improving the image of construction.

    Divisional Manager, James Jennings said: "The consistent high scores are a testament to site team members past and present. Stephen Smith has been a constant throughout these scores being achieved and has developed those working with him to bring them up to his expected high standards. It's an absolute pleasure working with Stephen and I'm pleased that his and the teams hard work and dedication is being recognised."

  • Works update - February 2024

    Welcome to our site works update for February

    February has seen the continuation of progress with the ongoing installation of ventilation ducting and sprinkler systems throughout the east wing.

    Structural surveys and investigations in the north wing have continued, the removal of scaffolding to the riverside elevation has now been completely removed.

    The continuation of M&E aspects including ceilings and walls being installed on the east wing is being progressed along with the completion of riser reinforcement. Preparation for the MVHR plant has started within the loft space along with the new insulation and boarding.

    We apologise for any inconveniences arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in March:

    East wing:

    • Continuation of wall and ceiling installations
    • Completion of M&E installations to remaining risers and flats

    New lobby entrance:

    • Commencement of landscaping, ground works and masonry package
    • Structural steel frame construction

    North wing:

    • Continued design related planning and surveys

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for February, please click here.

  • Works update - January 2024

    Welcome to our site works update for January

    Happy new year from Equans!

    We're back with our January update.

    January will see the continuation of progress throughout the east and west wing. New electric meters are continuing to be connected and fitted in the basement ready for the new supply to be connected.

    Structural surveys and investigations in the north wing are fully underway, the removal of scaffolding to the riverside elevation has now been completely removed.

    The continuation of M&E aspects including ceilings and walls being installed on the east wing is being progressed along with the completion of riser reinforcement. We apologise for any inconvenience arising from our works.

    Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

    What to expect in February:

    East wing:

    • Continuation of wall and ceiling installations
    • Completion of M&E installations to remaining risers and flats

    New lobby entrance:

    • Internal finishes and new entrance door installations
    • Commencement of landscaping, ground works and masonry package
    • Structural steel frame construction

    North wing:

    • Continued design related planning and surveys

    If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


    To view the full resident newsletter for January, please click here.

Page last updated: 24 Oct 2024, 12:35 PM