Works update - September 2024
Welcome to our site works update for September
August has seen the continuation of progress throughout the east and west wings and new entrance area.
M&E works within the risers is now complete allowing closing and fire-proofing to take place. Final plastering within the flats is now fully underway along with preparation to install kitchens and bathrooms.
The west wing ground floor communal area has been progressing well, both kitchens have been fitted along with carpentry and painting works.
As always, we apologise for any inconveniences arising from our works.
What to expect in October:
East wing:
- Commencement of kitchen and bathrooms
- Closing of risers
- Closing of walls and ceilings
- Plastering to walls and ceilings
- Paint works
- Window remediations
New lobby entrance:
- Installation of new central core steel works to lobby lift
North wing:
- Continued design related planning and surveys
West wing:
- Progression of ground floor west wing areas, and progression of garden/landscaping areas
- Progression of timber works to new entrance
If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.
To view the full resident newsletter for September, please click here.