Works update - South East & East Team - February 2024
We're pleased to provide an overview and update for the works currently being delivered by our South East & East team.
If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.
Works update for SHDF 2.1 works in Wisbech/March:
In summary, we completed the following throughout February:
- 49 properties on programme for Social Housing Decarbonisation Funded (SHDF) works for energy efficiency improvements. Improvements include; cavity wall insulation, loft insulation, soffit insulation, window & door installation, new mechanical ventilation in kitchen and bathroom. Some properties required asbestos removal from the soffits, thereby having replacement fascia, soffits and gutters
- 8 properties completed in February - 44 total across Wisbech and March
- 1 property has had ventilation fitted - 48 total
- 2 properties have had loft insulation extracted and refilled - 46 total
- 8 properties have had cavity wall insulation extracted and refilled - 48 total
- 11 properties have had window and door insulation - 48 total
- Scaffolding now down at all properties
- 2 properties have received removal of asbestos soffits by Clarion Asbestos contractor
- Insulation works completed to passageway ceilings at 4 properties
The site team for these works include;
Senior Site Manager - Mick Cawley
Assistant Site Manager - Karen Walker
Trainee Site Manager - Reuben Rule
Resident Liaison Officer - Claudia Paton