Works update - South East & East Team - July 2024
We're pleased to provide an overview and update for the works currently being delivered by our South East & East team.
If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.
Works update for SHDF 2.1 works in Wisbech/March:
In summary, we completed the following throughout June:
- We are currently working on properties programmed for 24/25 - 80 properties identified for Sustainable Homes work
- 1 property completed in July 2024
- 3 properties opened in July 2024 (37 total)
- 3 properties had cavity wall insulation completed in July 2024 (33 total)
- 1 property has had ventilation works completed within their kitchen and bathroom in June 2024 (28 total)
- Fascia, soffit and gutter replacements at 2 properties (14 total)
- 8 air source heat pump installations completed in July 2024 (12 total)
- Scaffolding erected at 1 property in Truman Avenue for asbestos soffit removal and fascia, soffit and guttering
- Scaffolding erected at 2 properties in Colvile Road for roof replacement works
- Roof works commenced at Colvile Road and ongoing - this involved removal of concrete gutters
- Windows and doors installed at 8 properties in July 2024 (9 total)
- Asbestos removal to 7 properties in July 2024 (13 total)
- 8 properties had door undercuts completed in July 2024 (18 total)
- Moving of gullies completed at Cannons Close & Colvile Road ready for external wall insulation
- Pre-ATT & modelling of properties ongoing
The site team for these works include;
Senior Site Manager - Mick Cawley
Assistant Site Manager - Karen Walker
Trainee Site Manager - Reuben Rule
Resident Liaison Officer - Claudia Paton