Works update - South East & East Team - August 2024

We're pleased to provide an overview and update for the works currently being delivered by our South East & East team.

If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.


Works update for SHDF 2.1 works in Wisbech/March:

In summary, we completed the following throughout August:

  • We are currently working on properties programmed for 2024/25 (80 properties identified for Sustainable Homes works)
  • 4 properties completed (5 total)
  • 1 property opened (38 total)
  • 1 property has had ventilation works completed within their kitchen and bathroom (29 total)
  • Fascia, soffit and gutter replacements at 1 property (15 total)
  • 3 Air Source Heat Pump installations completed (15 total)
  • 4 loft insulations completed
  • Roof works commenced at Colvile Road and ongoing
  • Windows and doors installed at 8 properties (17 total)
  • 14 soffit insulations completed
  • External wall insulation commenced at 4 properties in Wisbech, St Mary
  • Pre-ATT & modelling of properties ongoing

On the component works being carried out in Wisbech and Kings Lyn:

  • Scaffolding has commenced at Onyx Court, Wisbech to allow for licenced asbestos removal and the replacement of fascia, soffits and guttering
  • Scaffolding has been completed at Southgate Street, Kings Lyn so external decorations can begin
  • Scaffolding has been put up at 8 properties in Kings Lyn in August for fascia, soffit & guttering replacement (Evelyn Way, Segrave Road)
  • 7 properties have had window and door replacements in August
  • 3 new doors were installed at a residential scheme in Kings Lyn
  • Internal and external decorations have commenced for a residential scheme
  • New communal entrance and rear exit doors were installed at two blocks of flats in Cottier Drive, Littleport
  • New communal entrance doors were installed at 2 blocks of flats in Gilpin Place, Cambridge

For works being carried out in Peterborough:

  • We are currently working on properties programmed for 2024/25 - 50 properties identified for component works being carried out in Peterborough
  • We have completed and handed over 8 properties at Orchard Mews, Woodston including external decorations as well as 2 properties at Farriers Court including roofline works
  • Scaffolding has been completed at Farriers Court, so external roofline works can be completed (10 properties)
  • Scaffolding has been erected at 8 properties in August for bay windows and cladding replacement (Fen View)
  • For August we have completed and handed over 10 properties to Nicholas Beadle from Clarion

The site team for these works include;

Senior Site Manager - Mick Cawley
Assistant Site Manager - Karen Walker
Trainee Site Manager - Reuben Rule
Resident Liaison Officer - Claudia Paton