Works update - West Midlands team - November 2023

We're pleased to provide an overview and update for the works currently being delivered by our West Midlands team.

If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.


Tyler Court

Project progress:

Works currently on programme. As of 24th November:

Block 1 - All tiling and conversion of flat to pitched roof complete. Scaffold now being dropped for new drainage works to be connected.

Block 2 - Flat to pitched conversion now complete. All brickwork and truss extensions complete. Tiling in progress and approximately 60% complete.

Block 3 - Batoning out to gable ends and backs of mono pitched roofs. Extended trusses.

Block 4 - Asbestos removal in progress. Temporary roof covering in place.

Additional Works

Project progress:

Progressing as programmed, due to complete December 2023.

Completed social value initiatives:

  • Pre-employment training and work experience - both provided at Tyler Court for one individual who worked with the CLO throughout November. Seven pre-employment training courses delivered in Birmingham on 21st November
  • Apprenticeships and job starts - two apprenticeship opportunities and one job start at Birmingham
  • Specialise qualification sponsorship - £163.96
  • Financial contribution towards digital devices - £500
  • Clarion Futures donation - £400
  • Contractor engagement - One Meet the Contractor event at Tyler Court
  • Provision of equipment or services - £50

Planned social value initiatives:

  • Apprenticeship & job starts: Will be difficult to achieve in this within our current contract but we are actively sharing employment opportunities for job starts with Clarion on a monthly basis. Two apprentice positions and one CLO job start potentially awaiting interview confirmation
  • Accredited Training: Target achieved
  • Sponsorships & donations: Target achieved
  • Employment, Training & Work Experience: Target achieved
  • Digital Training: Awaiting Clarion approval
  • Refurbishment projects: £500 allocated towards projects
  • Contractor engagement: Target achieved, plus Christmas engagement event planned with donations of gifts for Tyler Court residents
  • School engagement: Target achieved
  • Staff volunteering: Finance team offered online training at community centre, awaiting Clarion approval