Works update - West Midlands Team - September 2023

We're pleased to provide an overview and update for the works currently being delivered by our West Midlands team.

If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.


Tyler Court

Project progress:

Works currently on programme. First block roof removed. Second block receiving temporary roof covering and third block has scaffold erected.

Additional Works

Project progress:

Progressing as programmed.

Completed social value initiatives:

  • Specialise qualification sponsorship - £163.96
  • Financial contribution towards digital devices - £500
  • Clarion Futures donation - £400
  • Contractor engagement - One Meet the Contractor event at Tyler Court
  • Provision of equipment or services - £50
  • Accredited training - CSCS training completed 29th September

Planned social value initiatives:

  • Apprenticeship & job starts: Will be difficult to achieve in this within our current contract but we are actively sharing employment opportunities for job starts with Clarion on a monthly basis
  • Accredited Training: Target achieved
  • Sponsorships & donations: Target achieved
  • Employment, Training & Work Experience: 'Skill for Success' training offered, awaiting Clarion approval
  • Contractor engagement: Target achieved
  • School engagement: Mock interview sessions planned at Wood Green Academy on 10th October and Joseph Leckie Academy on 24th October
  • Staff volunteering: 'Skill for Success' training - awaiting Clarion approval