Resident Newsletter - March 2025

Welcome to your resident's update from Equans. This is a great way for us to keep you up to date with all the work that has been going on so far and what we expect to achieve going forward.

If you have any queries about the works being undertaken by Equans, please direct your query to your appointed Resident Liaison Officer, Carole Coleman by calling 07880 786 442.


As you will be aware, Equans has been appointed by Southern Housing to replace cladding and associated fire remediation works at Cygnus Court. We would like to extend our sincere thanks, gratitude and appreciation for your patience, support and understanding during the fire remediation works.

Some of our progress so far:

  • All rendering works will be complete by Friday 21st March and all of your balconies will be back in your possession for your enjoyment once more before this date.
  • The containers will be removed on Monday 31st March. Please be aware we will have a static presence of a lorry-loaded crane and access to the car park side will be almost impossible during the hours of 8am & 5pm, just for that day.
  • Any internal damage which we feel are down to our works are being assessed presently and we foresee remedial works will start to be undertaken w/c 24th March but possibly later, please bear with and we will advise accordingly.

Our next residents meeting:

  • Our next residents meeting is on Tuesday 26th March from 6pm-7pm.

Please click here to view a copy of the full Resident's Newsletter.