Progress update - October 2023

We're pleased to provide you with our October update - this information was taken from the slides presented at the last residents meeting held on 2nd November. If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.

Phase 1:

  • Installation of new Sheathing Board - 100% complete
  • Installation of EPDM around openings - 100% complete
  • Installation of zinc cladding - 55% complete
  • Installation of Cedral Lap to balcony soffits - 30% complete
  • Installation of Cedral Lap to walls - 10% complete
  • Balcony remedial works - 65% complete

Phase 2:

  • Removal of cladding - 90% complete
  • Installation of new Sheathing Board - 90% complete
  • Installation of EPDM around openings - 90% complete
  • Installation of zinc cladding - 90% complete
  • Installation of Cedral Lap to balcony soffits - 30% complete
  • Installation of Cedral Lap to walls - 15% complete

Phase 3:

  • Scaffolding - 100% complete
  • Removal of cladding - 90% complete
  • Removal of existing decking - 90% complete
  • Installation of new Sheathing Board - 5% complete
  • Installation of EPDM around openings - 5% complete

Balcony Drainage: All but four properties have been surveyed and NHG have instructed Equans to carry out remedial re-screeding works as necessary. All balconies are being treated to improve the removal of lying water. Works to Phase 1 are complete and Phase 2 has commenced.

Terrace Insulation: Ashton Fire reviewed on 10th August - replacement not required.

Statutory works on High Street: Forecast completion date is mid-November.

Programme Completion Dates:

  • Phase 1: West & South elevations - 23rd January to 19th December 2023 - delayed due to balcony remedial works
  • Phase 2: High Street & Plaza - 12th March to 19th December 2023 - delayed due to balcony remedial works and statutory authority works
  • Phase 3: Courtyard - 1st May 2023 to 8th April 2024 - delayed due to balcony remedial works
  • Site Decant: 15th April 2024

Please click here to view a full copy of the slides from the residents project meeting held on 2nd November.