Resident Meeting Minutes - 12th March

We are pleased to share with you, the minutes from our last Resident's meeting from 12th March 2024. If you have any queries or concerns about the works being carried out by Equans, please contact your site team.

Important notes:

Reported intruder on scaffolding: If you ever see any unauthorised persons on the scaffolding, particularly at night, please immediately report this to the Police and then to the Equans RLO. The scaffolding is alarmed, and the alarms have been checked recently. They are working as we expect them to.

Respectful behaviour: We appreciate that the project has been ongoing for some time now and the disruption is becoming frustrating as we near the end. However, we implore you all to please be patient and kind to the site team. There have been reports of aggressive behaviour which we will not tolerate. Please report any issues to the RLO.

Progress update

Phase 1:

  • New facade installation 95% complete
  • Screeding and remedial works to balconies 100% complete
  • Balcony soffits 95% complete
  • Balcony decking 95% complete
  • Scaffold striking 90% complete

Phase 2:

  • Erection of scaffolding 100% complete
  • Removal of zinc cladding 100% complete
  • Window EPDM 100% complete
  • New facade installation 90% complete
  • Screeding and remedial works to balconies 100% complete
  • Balcony soffits/decking 90% complete

Phase 3:

  • Removal of existing balcony soffits and decking 100% complete
  • Remove glazed balustrades and set aside 100% complete
  • Removal of zinc cladding 100% complete
  • Window EPDM 90% complete
  • New facade installation 75% complete
  • New zinc installation 20% complete
  • Screeding and remedial works to balconies 100% complete
  • Balcony soffits and decking 75% complete
  • Strike scaffolding 10% complete

Programme Completion Dates:

  • Phase 1 West & South Elevations: Remainder of first floor level will be struck week commencing 18th March 2024
  • Phase 2 High Street & Plaza: Area to the entrance, down by the end of week commencing 11th March 2024. The remaining scaffold for high level penthouse will be struck week commencing 25th March 2024
  • Phase 3 Courtyard: First level to the east elevation will be struck from week commencing 18th March 2024. This is progressing faster than we previously advised
  • Site decant: 22nd April 2024

This update has been extracted from the presentation given to residents at the Resident's Meeting held on 12th March, please click here to view a copy of the presentation slides in full.


<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>