Resident meeting minutes - 30th January

We are pleased to share with you, the minutes from our last Resident's meeting from 30th January 2024. If you have any queries or concerns about the works being carried out by Equans, please contact your site team.

Progress update

Phase 1:

  • New facade installation 90% complete
  • Screeding and remedial works to balconies 100% complete
  • Balcony soffits 65% complete
  • Balcony decking 45% complete
  • Scaffold striking 25% complete

Phase 2:

  • Erection of scaffolding 90% complete
  • Removal of zinc cladding 90% complete
  • Window EPDM 100% complete
  • New facade installation 90% complete
  • Screeding and remedial works to balconies 100% complete
  • Balcony soffits/decking 90% complete

Phase 3:

  • Removal of existing balcony soffits and decking 100% complete
  • Remove glazed balustrades and set aside 100% complete
  • Removal of zinc cladding 100% complete
  • Window EPDM 85% complete
  • New facade installation 55% complete
  • Screeding and remedial works to balconies 90% complete

Programme Completion Dates:

  • Phase 1 West & South Elevations: 23rd Jan 2023 - 29th February 2024.
  • Phase 2 High Street & Plaza: 13th Mar 2023 - 29th February 2024. Delayed due to statutory authority works
  • Phase 3 Courtyard: 1st May 2023 - 8th Apr 2024
  • Site decant: 15th April 2024

This update has been extracted from the presentation given to residents at the Resident's Meeting held on 30th January, please click here to view a copy of the presentation slides in full.


<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>