Resident update - August 2024

Welcome to our site works update for August

If you have any queries about the works being carried out please speak to your allocated Resident Liaison Officer, Carole on 07880 786 442.


Our progress so far:

  • We have started the insulation on the SW and SE elevations of the building, which is going well
  • We are installing Hardie Plank on the SW elevation
  • We continue to finish the T-Profile and STO-Ventec

Our next steps:

  • The next stage is to install the STO-Ventec render rainscreen system, Hardie Plank and insulation
  • The balconies post have been approved and are at the process of manufacturing

Resident evening meeting: We will be holding our next resident meeting via Microsoft Teams on Wednesday 11 September from 6-7pm. You are all invited and an email invitation will be sent out closer to the time. We look forward to seeing you.

Our respite room:

  • Place for residents to discuss issues relating to the ongoing works, have tea or coffee and biscuits while watching television
  • Place to get an update on day-to-day work activities on site via our bulletin board and microsite
  • Place to register your comments, suggestions, complaints and compliments through our suggestion box

This update has been extracted from the August Resident Newsletter, please click here to view this in full.