Resident update - January 2024

Welcome to our site works update for January

If you have any queries about the works being carried out please speak to your allocated Resident Liaison Officer, Carole on 07880 786 442.


Our progress so far:

  • Additional propping to balconies to give extra support when works are carried out in that area
  • Currently checking insulation and putting Y wall (fire resistant board) back on

Our next steps:

  • Removal of block work
  • Second hoist to be installed to the front of the building