Resident update - May 2024
Welcome to our site works update for May
If you have any queries about the works being carried out please speak to your allocated Resident Liaison Officer, Carole on 07880 786 442.
Our progress so far:
- All block works have been removed from the building
- All fire rated Y wall board has been installed
- The moisture resistant tape between the joints on the Y wall has been installed
- We are installing EPDM around all windows and balcony doors
Our next steps:
- Install breathable membrane and C channels on the building
- We are awaiting receipt of the survey report on the balconies from our Structural Engineers
Our respite room:
- Place for residents to discuss issues relating to the ongoing works, have tea or coffee and biscuits while watching television
- Place to get an update on day-to-day work activities on site via our bulletin board and microsite
- Place to register your comments, suggestions, complaints and compliments through our suggestion box
We will be holding a resident meeting via Microsoft Teams on 5th June from 6-7pm. An email invitation will be sent to you closer to the time. We look forward to seeing you there.