Chelsea Court


Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.

As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.

We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.

The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.



Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.

As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.

We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.

The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.


  • Works update - March/April

    Welcome to our site works update for March/April

    March and April has seen encouraging progress in all elements of works currently on site. The soft landscape of the new entrance area has commenced as well as continuation of the foundation build up.

    On the east wing we are continuing with general build works, which includes various necessities of your new properties, examples of this are build up of floors, riser construction, and enabling first fix for services.

    To add, can we kindly request to not enter any of the live working construction areas and any queries or requests should go through the Scheme Manager, Alex.

    What to expect in May

    • Continued general build on east wing and west wing ground floor communal areas
    • Continued works on new entrance and landscaping of surrounding areas

    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


    Please click here to view the latest resident newsletter in full.

  • Team achieve third consecutive top score from Considerate Constructors Scheme

    The team at Chelsea Court have once again achieved an amazing top score of 45/45 from their recent audit visit by the Considerate Constructors Scheme (CCS) making it their third consecutive top score.

    Upon hearing the news Divisional Manager, James Jennings commented: "This is an amazing achievement which the whole team should be immensely proud of - well done to all involved."

    When the CCS monitor visited the scheme recently to carry out their audit of the site, they commented things like "There is extensive liaison with both the client's representative on the site and residents. There's an excellent level of engagement with all those affected by the works."

    The CCS is an independent organisation founded to raise standards in the construction industry to ensure all construction sites present an image of competent management, efficiency, awareness of environmental issues and above all neighbourliness. Monitors from the scheme regularly audit our sites to ensure we are adhering to the scheme’s Code of Considerate Practice which is designed to encourage best practice beyond statutory requirement.

    Each audit is split into three categories; respect for the community, protecting the environment and valuing the workforce each with a potential score out of 15 with a total combined max score of 45 available. To score above 13 in any category warrants an excellent level of achievement for that category.

    Congratulations to Site Managers, Sergiu and Adie and the rest of the site team, who work so hard every day to maintain such high standards

    Click here for a short video to celebrate our score.

  • Works update - February

    Welcome to our site works update for February

    February has seen positive development in a range of works currently on site. The foundation works required for the new entrance is currently under construction with good progress being made.

    On the east wing we are underway with general build works, which includes various elements of construction such as dry lining, fire proofing, riser formation and much more.

    To add, we can happily report that no near misses or incidents have happened on site during the month of February at Chelsea Court.

    What to expect in March

    • All demolition works to be completed on site
    • Continued general build on east wing and west wing ground communal areas
    • Isolation of heating on the entire building for a period of time, dates yet to be confirmed, temporary heating will be provided.


    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


    Please click here to view the February resident newsletter in full.

  • Works update - January

    Welcome to our site works update for January

    January has seen good progress in all elements of works on site, firstly with the start of the demolition of the link bridge. This has now allowed us to dismantle the scaffold to a level which enables demolition of the lower section.

    Currently we are stripping the flats out so that we can begin the building works to refurbish the flats as soon as this is completed.

    We are also happy to inform you that the bell tower works have now been completed.

    What to expect in February

    • Lower section demolition of old link bridge
    • Continued works on the east wing and west ground communal
    • Main entrance investigation in progress to restore normal services
    • Isolation of heating to the entire building for a period of time, dates yet to be confirmed - temporary heating will be provided

    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


    Please click here to view the January resident newsletter in full.

  • Works update - December

    Welcome to our site works update for December

    Seasons Greetings

    The Equans site team would like to thank you for your patience and understanding during our construction works on this scheme. We will be closing the site over the festive period from Thursday 22nd December and re-opening Tuesday 3rd January 2023. If you see any unauthorised people trying to access our site during this period, please call the Police immediately.

    From all of us at Equans we wish you a Merry Christmas and a happy new year.

    Site update

    Since our last update, we have completed the isolation of all services in east wing properties (5th floor to ground) and we are currently working through the planned demolition process which is nearly complete.

    We are currently working through structural, mechanical and electrical investigations once areas are exposed.

    We are also finalising refurbishment of the east wing bell tower, doing the final touches with lead installation on the turret.

    In the new year we will be starting the demolition of the old entrance bridge and the new entrance extension.

    What's next?

    In January and February 2023 we will complete all associated demolition works and start the construction of your soon to be new east wing.

    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.

  • Home User Guide available

    We have received a number of questions about taking care of your property and how to work your appliances. Answers to these frequent questions can be found within the Home User Guide provided by Peabody which is also available within the Documents Library on this website.

    As a reminder, the guide provides you with advice and tips on how to get the best out of your home - as well as addressing any problems that may occur. Useful information about the local area and important services nearby have also been included. Please read the guide carefully and keep in a safe place for reference.

    Disclaimer: While all information was correct at the time of producing this guide, Peabody and Equans cannot be held liable for any changes that may render it incorrect. In addition, this guide is not a guarantee for any of the equipment or services described within it.


    Click here to view the Home User Guide in full.

  • Works update - November 2022

    Welcome to our site works update for November

    Site update

    Access to the east wing is now restricted to the residents.

    Current works

    The east wing is currently being surveyed. Isolation of the services i.e. water, heating, and electricity have now been shut off - as a result of these works the heating system had some minor issues but we are working hard to resolve this as soon as possible, we apologise for any inconvenience caused. Hard and soft strip have started and are due to be complete before Christmas.

    Remedial work

    As a reminder for those living in the west wing, please note any works you would like the handyman to carry out in your apartment. The handyman will perform tasks such as mounting shelves, blinds, TVs, coat hooks, picture frames, and assembling flat-pack furniture etc. Please then pass your list to Peabody's Scheme Manager, Alex to be communicated to the site team.

    Further update

    Scaffolding has been erected around the west wing due to a leak. Alex will be in contact with the residents affected.

    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.

  • Site team achieve top marks from Considerate Constructors Scheme!

    The Equans site team at Chelsea Court received an amazing score of 45/45 from their recent audit visit by the Considerate Constructors Scheme (CCS) after scoring top marks in each of the three categories.

    On 17th October, a CCS monitor visited the scheme and carried out their audit of the site, commenting things like "This is an excellent project which is demonstrating robust commitment to the CCS Code of Considerate Practice. The site was seen to be very clean, tidy and well organised. The provision of a site specific microsite is commendable. Emphasis is placed on consideration for the elderly residents and the site team strive to ensure that there is minimal disruption whilst the works are in progress."

    The CCS is an independent organisation founded to raise standards in the construction industry to ensure all construction sites present an image of competent management, efficiency, awareness of environmental issues and above all neighbourliness. Monitors from the scheme regularly audit our sites to ensure we are adhering to the scheme’s Code of Considerate Practice which is designed to encourage best practice beyond statutory requirement.

    Each audit is split into three categories; respect for the community, protecting the environment and valuing the workforce each with a potential score out of 15 with a total combined max score of 45 available. To score above 13 in any category warrants an excellent level of achievement for that category.

    Congratulations to Site Manager, Sergiu and the rest of the site team, who work so hard every day to maintain such high standards

    Click here for a short video to celebrate our score.

  • Works update - October 2022

    Welcome to our site works update for October

    Site update

    Relocation of residents from both the north and east wings has been completed. Those that remained in the east wing have been relocated to the north wing in preparation for phase 2 of the works.

    Access to the east wing will now be restricted to the residents.

    Current works

    The east wing is currently being surveyed. Services are being isolated i.e. water, heating, and electricity are being shut off.

    Remedial work

    As a reminder for those living in the west wing, please note any works you would like the handyman to carry out in your apartment. The handyman will perform tasks such as mounting shelves, blinds, TVs, coat hooks, picture frames, and assembling flat-pack furniture etc. Please then pass your list to Peabody's Scheme Manager, Alex to be communicated to the site team.

    Further update

    Scaffolding has been erected around the west wing due to a leak. Alex will be in contact with the residents affected.

    If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


    Click here to read the full newsletter

  • Happy Halloween from Equans

    From all of us at Equans, we wish you a happy Halloween.


    A children's activity pack can be collected from your Resident Liaison Officer. Alternatively this can be viewed and downloaded from our 'Documents Library'.

    Please be careful if carving pumpkins and stay safe whilst trick or treating.

Page last updated: 24 Oct 2024, 12:35 PM