Seren Park - Cladding Replacement
Welcome to the Seren Park Scheme Microsite. Here you will find the latest news, updates of works being carried out on site, contact details for site staff, event information, photos, and resident documents.
Completing this scheme on behalf of Seren Park Gardens RTM Company Ltd is Equans and Martin Arnold, details on their roles and responsibilities can be found below:
Martin Arnold Ltd – Contract Administrator
Martin Arnold are the designers of the cladding remedial works. Martin Arnold will project manage the works on behalf of Seren Park Gardens RTM Company Ltd and administer the formal building contract between Seren Park Gardens RTM Company Ltd and Equans. Martin Arnold will also have a daily Clerk of Works on site who will be inspecting the quality of the workmanship.
Equans - Contractor
Equans has been successfully appointed to undertake the removal and replacement of the existing external cladding at Seren Park Gardens.
As per Seren Park Gardens RTM Company Ltd requirements, the cladding panels will be removed and replaced in sections and instalments, ensuring each flat remains watertight at the end of each working day.
HAUS
HAUS Block Management are the property managers on behalf of Seren Park Gardens RTM. If you have cladding related questions to ask HAUS, please make contact through the HAUS portal on http://h-portal.co.uk or sign up to the portal if you have not already done so.
Alternatively, you can contact HAUS on SerenParkGardens-cladding@h-bm.co.uk for additional information or if you have any questions.
Welcome to the Seren Park Scheme Microsite. Here you will find the latest news, updates of works being carried out on site, contact details for site staff, event information, photos, and resident documents.
Completing this scheme on behalf of Seren Park Gardens RTM Company Ltd is Equans and Martin Arnold, details on their roles and responsibilities can be found below:
Martin Arnold Ltd – Contract Administrator
Martin Arnold are the designers of the cladding remedial works. Martin Arnold will project manage the works on behalf of Seren Park Gardens RTM Company Ltd and administer the formal building contract between Seren Park Gardens RTM Company Ltd and Equans. Martin Arnold will also have a daily Clerk of Works on site who will be inspecting the quality of the workmanship.
Equans - Contractor
Equans has been successfully appointed to undertake the removal and replacement of the existing external cladding at Seren Park Gardens.
As per Seren Park Gardens RTM Company Ltd requirements, the cladding panels will be removed and replaced in sections and instalments, ensuring each flat remains watertight at the end of each working day.
HAUS
HAUS Block Management are the property managers on behalf of Seren Park Gardens RTM. If you have cladding related questions to ask HAUS, please make contact through the HAUS portal on http://h-portal.co.uk or sign up to the portal if you have not already done so.
Alternatively, you can contact HAUS on SerenParkGardens-cladding@h-bm.co.uk for additional information or if you have any questions.
-
New letter: August update on our works
This article has been summarised, a full copy of the letter is available within the documents library.
Following on from our last update, the legal process to terminate our main subcontractor's contract was completed allowing us to appoint replacement contractors for the completion of the works.
During the re-appointment phase, to maintain some progress we utilised an existing contractor to complete the removal of all remaining zinc areas and associated insulation. The specialist zinc contractor received their order at the end of July resulting in commencement on site Monday 31st July, restarting the installation of the new zinc finishes and compliant insulation.
We fully expected our preferred contractor for the main render and cladding areas to have received their works order and have commenced on site. Unfortunately, due to a number of issues, this has been delayed. These issues have now been resolved and the order is due to be completed next week allowing for a start on site from 21st August. During the last few weeks, the contractor's management team have been on site surveying and preparing for start on site.
Our June newsletter included an indicative completion programme, we are now in a position to complete an accurate project completion programme. Once finalised and agreed with all the necessary stakeholders this will be shared with all interested parties.
-
Keep your kids entertained during summer with our free activity pack...
Equans' Working Parents Network have produced an activity pack to help keep children entertained throughout the summer holidays - click here to download a copy.
We understand that it's difficult to keep children entertained throughout summer, especially whilst you're working or maybe you've run out of ideas of things to do - well maybe we can help with that..
Our summer activity pack includes a number of drawing activities including word searches, puzzles and spot the difference as well as useful tips, recipes and ideas for days out.
Click the link above to view and download your free copy.
-
New letter: Balcony Zinc Cappings (Flats 116, 122, 128, 134, 140 & 146)
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to inform you, commencing Friday 23rd June, Equans will have operatives working directly on your balcony installing zinc cappings.
To facilitate these works, access will be required onto your balcony. We will be working directly on your balcony and around lounge and bedroom windows. For your privacy please keep curtains and blinds closed - to minimise any dust particles going into your property, closing windows could help prevent this, but it is your responsibility and choice in taking in measure.
Very importantly, could you please ensure that all personal belongings i.e. bicycles, plants, garden sets, storage boxes, sheds, bird netting, bird spikes etc. are cleared to allow for the works. Please be advised that Equans cannot accept responsibility for any damage or loss caused to items that have not been cleared.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 725 as soon as possible for guidance, alternatively you can also contact Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
-
New letter: Zinc stripping works commencing (Flats 24, 25 & 68)
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to inform you that from Monday 3rd July, one of our newly appointed subcontractors, PJ Foley will start stripping off the zinc panels from balcony level. We anticipate these works to be completed in approximately three weeks, weather permitting.
We understand because of the location and particular circumstances, we will liaise with you before any works commence.
To facilitate these works, access will be required onto your balcony/terrace. We will be working directly on your balcony/terrace and around lounge and bedroom windows. For your own privacy, please keep curtains and blinds closed.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 725 as soon as possible for guidance, alternatively you can also contact Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
-
June works update
Welcome to your latest works update. You will have also received this as a hard copy in the form of your resident newsletter.
If you have any queries or concerns about the works being undertaken by Equans, please contact Senior Resident Liaison Officer, Christine Todd on 07766 420 977.
General update
The Seren Park Gardens cladding replacement scheme commenced February 2022 and was due to complete May 2023. Following the addition of works to the podium landscaping a revised completion of August 2023 was submitted and agreed.
Works were progressing well until late 2022 when issues arose with our main subcontractor. Following communications received early 2023 it became apparent they were in some financial difficulty. A new director and management team were introduced and Equans agreed some measures to assist with the completion of works.
With the new management and assistance from Equans, progress on site increased and was approaching the levels required to complete the contract to the revised date. However, following further issues with the main subcontractor we were advised in April 2023 that they were entering liquidation. Progress on site has been extremely limited whilst we have been going through the legal process of contract termination. This is nearly complete and has allowed us to approach alternative contractors to complete the works.
All works to date at the various stages of completion have been checked and verified by the appropriate independent bodies to confirm compliance with required regulations. To ensure as seamless a transition as possible, Equans are in the process of appointing the subcontractors who carried out the removal and replacement of various finishes for the previous contractor where possible.
An experienced and proven contractor is being approached where this is not possible, we have currently re-programmed to complete in late November 2023.
Redecoration works
Redecoration works have started and further appointments will be made in due course. Sections 1 and 2 will be prioritised followed by Section 3 once the top coat render has been applied and all cap flashings installed to ensure the building is fully water tight.
Bulkhead Balcony Lights
Appointments will be made to access your property and balconies where bulkhead lights were removed last year. New bulkhead lights will be re-instated. Your RLO will contact you and further pre-condition photos will need to take place. We ask that residents please dispose of any old bulkhead lights.
Works update - sections
Sections 1 to 4: Scaffolding to these sections are complete, with minor adaptations required as works progress. Work to remove the existing cladding systems on these sections is virtually complete with a couple of high level external lift over-run structures to strip at roof level.
Section 1: Zinc / Rockpanel and external wall insulation (EWI) is virtually complete, with minor items of snagging and remedial works to complete before scaffold is struck. Scaffold striking on Section 1 will re-commence very shortly once operatives return to site and snagging works are complete.
Section 2: The powder coated in-set balcony coping flashings are currently being installed by a separate subcontractor. Zinc / Rockpanel and EWI is virtually complete, with minor items of snagging and remedial works to complete once the newly appointed subcontractors start on site before scaffold can be struck any further. Scaffolding has already been struck from the 9th floor and part of the 8th floor.
Section 3: This is the largest single section of the job and has been split into LHS and RHS for reference. Works have commenced on the Zinc carrier system installation at high level on both sides, EWI insulation fully installed where accessible and all areas base coated and primed. The final top coat of render should follow once the newly appointed subcontractors start on site. Following the final render coat and a brief drying/curing period, the render should be ready to receive the final two coats of paint.
For information, the render system is not complete to Section 3, the primer coat looks like finished white paint, however, the final top coat of render and two coats of paint are still yet to be applied, so please do not be concerned as this is not the final finish.
Section 4: Balcony wall to decking flashings and fire barriers have already been installed and the final Rockpanel cladding has been installed to various floors.
Section 5 & 6 (Podium area): The scaffold to both sections is complete. The original cladding and render EWI system has been removed with the exception of elements around the doorways which is still being co-ordinated with the intercom and CCTV installers. The remaining elements of existing zinc at high levels will be prioritised for removal as soon as works re-commence. EWI insulation and render, Rockpanel and zinc works will be underway once the newly appointed subcontractors start on site, starting on Section 5, then moving around to Section 6.
External balconies: Decking replacement will again re-commence once operatives are back on site. Decking replacement involves stripping out the existing decking boards, removing the timber sub-frame, installing a fire-break between the balcony steelwork and wall and installing a cover flashing with an EPDM waterproofing membrane tight under the balcony door / windows.
New aluminium box sections will be fixed to the existing steel frame and the new aluminium decking boards are fixed to the box sections, up to the scaffold tubes penetrating the balcony, stopped and then re-started. One or two of the old boards will be left in the gap for safety reasons and replaced with new aluminium decking once the scaffold is removed floor by floor.
In-set balconies (Only on Sections 1-3): All in-set balconies have been waterproofed and the in-set balcony decking is virtually complete to Sections 1-3 where direct scaffold access is available. Four balconies are left to complete, however two balconies are holding water which are currently being discussed as a design issue. Coping flashings to the lower face of the balconies are currently being installed to Section 2 and this will be followed by Section 1. Section 3 copings will be installed after the final coat of render and painting.
Scaffold security and emergency measures
Scaffold fire alarms have been installed externally on the scaffold in various locations. These alarms are not automatic and will only be activated manually in the event of a fire, fire drill, or accidental operation. In the event of an actual fire, emergency services will be contacted immediately, the concierge will be notified via Walkie-Talkie/phone and your own Seren Park fire plan will be put into action.
Fire drills - You will be notified well in advance via letter, notice board and Facebook and for this you will be advised to remain in your property. This will be a fire drill for Equans staff and contractors only. Accidental operation of fire alarms should be extremely rare - in the event that this happens, we can silence the alarms remotely. The Site Manager is also the Fire Marshall and will make this assessment as a priority and ensure all residents are aware that this is a false alarm as soon as possible.
Cameras have been installed to the scaffold in various locations and are only activated by a trespass incident during non-working hours. Any access to the scaffold during out of hours is picked up automatically by a remote incident controller and escalated to the Police. Footage from the camera is also sent to Equans for record purposes.
Any other business
As previously reported, we have video evidence of an intruder on the high level scaffolding outside of our working hours. Access directly on to the scaffolding was gained from one of the apartments so can we please reiterate the dangers of these actions and ask that you all take whatever steps necessary to ensure this is communicated to all visitors etc.
Access to the concierge and podium is not restricted for residents, however, access to the podium is at your own risk due to the ongoing works. We do ask that you access and egress your block via the ground floor where possible and for food deliveries, residents must meet the delivery drivers at the front gate.
Works to all balcony areas are now in progress and we can't stress enough that you all follow any of our guidelines regarding these or any other works. Please do not access your balconies between the working hours of 8am-5pm Monday to Friday. The safety of you and our workforce must be the first priority.
Copies of EICR certificates can be issued via email for those who ask for them, please contact Senior RLO, Christine Todd.
The RTM and Equans are actively looking for a solution for capturing the water leaking from the podium into the under croft car park below and we are aware that this is an ongoing issue that's being dealt with.
There's been a number of leaks going into various properties since the original cladding has been removed, we are endeavouring to stop this happening moving forward. If you have experienced a water leak since the works began you should have received a visit from someone in the Equans team to have a look at any water damage immediately after the event and at least another visit to check on the drying progress. Equans will look at each property individually and respond in due course to let you know the process if any remedial works are required.
Notice to residents:
- Please ensure that you have contacted your insurance company regarding the scaffolding to your property and the risk of damage caused by the works (contents insurance)
- Please ensure that you remove anything fixed to the external walls where there's a possibility that vibrations could make these items fall, such as pictures and mirrors. Also move any chests of drawers that have pictures, ornaments or fragile items on top slightly away, so not touching the outside walls
- Please re-secure your window restrictors inside the housings fixed to the window frame. The restrictors will damage the new window sills if left loose and Equans will not be responsible for repairing or replacing the sills
- Do not keep any fragile items on the window sills as they are too narrow and items can fall off due to wind or vibration
- Please note that under your lease agreements, with sufficient notice, Equans/RTM are permitted to access properties
- If you notice a fishy or chemical smell from outside, this may be emanating from the fire-proof Rockwool insulation. This smell will dissipate over time once covered with render
- Pigeon netting is not being re-instated to balconies due to fire risk as advised by the Fire Engineer
- Structural alterations made by the residents are not permitted under the lease agreements
- Friendly request: To help us identify flats when on scaffolding, could you please place a label/sticker of your flat number on internal face of windows (labels available on request from Senior RLO, Christine)
- Important notice: Residents must be aware that it is your responsibility as the leaseholder/tenant to move ALL items off balconies, despite whether the items were present when moving in. The RTM and HAUS have confirmed that there is no storage on site for personal items
- Again, we would like thank those residents that have come to Equans directly to advise of loss of the parking bays which in certain circumstances is as a result of materials, or our operatives. We are doing all we can to mitigate these issues in the future but appreciate you working with us on this matter.
Rockwool's response: "I would say that the occurrence of an odour in Rockwool/rolls is extremely rare. As I'm sure you are aware Rockwool insulation is manufactured from stone which is melted and spun into fibres and the cured in an oven to form the insulation slabs; during the manufacturing process we add resins and oils to these fibres, to help bind the fibres together and improve the water repellency.
Other Rockwool companies have found that a release from these resins under certain conditions, can cause an odour if the product becomes wet. This odour is often most noticeable upon unpacking but will dissipate over a short period of time, dependent upon the level of ventilation the product is subject to. The presence of this odour in no way detracts from the performance of the product and presents no hazard to health."
Pigeons: It has been brought to our attention that pigeons are nesting on balconies and under scaffolding. On your balcony which you have access to, it's the tenant's/leaseholder's responsibility to deter the pigeons from nesting.
Balcony clearance and storage space: Please ensure that your balcony is cleared of all personal belongings during works. Equans cannot be responsible for any damage or loss of items. There is no storage space on site for residents' personal items to be stored.
Final note
We would like to thank all residents for their collaborative approach with the delivery of this project as we fully appreciate that these level of works increase numerous inconveniences to you all i.e. Equans receiving deliveries, skip deliveries/collections, noise pollution etc. We also appreciate those residents assisting with the clearance of their balconies allowing our operatives access to undertake our planned works.
We will be contacting residents in each section separately in advance of works starting in their vicinity and keeping them updated throughout.
Should any residents require assistance with entering or leaving the car park via the access road please let Christine know. Our on-site Traffic Marshal will be happy to assist. If you accidentally hit the scaffolding, please let us know immediately to enable us to carry out any necessary safety checks.
-
New letter: Zinc stripping works commencing (1-218)
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to inform you that from Monday 19th June, one of our newly appointed subcontractors, PJ Foley will start stripping off the zinc panels ahead of replacement works. The stripping of the zinc panels will continue on the main façade of the building, then drop back onto the higher level recessed properties. We anticipate these works to be completed in approximately three weeks, weather permitting.
Please also note that our forklift and skip will be returning to site, week commencing Monday 19th June 2023.
To facilitate these works, access will be required onto your balcony/terrace. We will be working directly on your balcony/terrace and around lounge and bedroom windows. For your own privacy, please keep curtains and blinds closed.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 725 as soon as possible for guidance, alternatively you can also contact Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
-
New letter: Balcony Zinc Cappings (Flats 34, 35, 40, 41, 46, 47, 52, 53, 59, 65 & 66)
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to inform you, commencing Monday 12th June, Equans will have operatives working directly on your balcony installing zinc cappings.
To facilitate these works, access will be required onto your balcony. We will be working directly on your balcony and around lounge and bedroom windows. For your privacy please keep curtains and blinds closed - to minimise any dust particles going into your property, closing windows could help prevent this, but it is your responsibility and choice in taking in measure.
Very importantly, could you please ensure that all personal belongings i.e. bicycles, plants, garden sets, storage boxes, sheds, bird netting, bird spikes etc. are cleared to allow for the works. Please be advised that Equans cannot accept responsibility for any damage or loss caused to items that have not been cleared.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 725 as soon as possible for guidance, alternatively you can also contact Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
-
Project update from Martin Arnold
As you may be aware, progress of the external façade cladding works has practically stopped in recent weeks. Due to contractual constraints Equans have been unable to share specific details regarding the lack of progress, but can now do so. Unfortunately, despite Equans’ best efforts and measures put in place to assist, Equans have had no choice but to terminate the contract of the main cladding sub-contractor who was doing the works.
However, Equans can now legally progress with appointing a replacement sub-contractor to carry the works through to completion. This process has commenced although there will be some delay before we are fully up and running again and a completion programme can be produced. This will be provided at the AGM meeting for leaseholders on 30 May 2023.
There are minor elements of work that Equans can progress without a sub-contractor and these are continuing.
Moving forward Equans will now be able to respond to any specific queries you may have. Please contact Christine Todd on 07766 420 977 in the first instance.
Please accept our apologies for any issues the current situation may be causing.
-
New letter: Scaffold strike from levels 8 & 9 at Section 2
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to advise you that the scaffolding to Section 2 - Levels 8 & 9 are scheduled to be dismantled commencing Thursday 30th March 2023 and will take approximately 3 days.
Please note that only Equans employees and their representatives are permitted access to scaffolding. For your own safety, no other persons are allowed to climb onto the scaffold under any circumstances. This applies particularly to children. Any unauthorised persons accessing the scaffolding outside of our normal working hours of Monday to Friday 8am-5pm should be immediately reported to the Police.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 725 as soon as possible for guidance, alternatively you can also contact Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
-
New letter: Zinc stripping on Sections 5 & 6
This article has been summarised, a full copy of the letter is available within the documents library.
We are writing to inform you, that we have started stripping the remaining Zinc panels from the high levels starting on Section 5 then moving onto Section 6. We anticipate these works to be completed in approximately three weeks, weather permitting.
To facilitate these works, access will be required onto your balcony/terrace. We will be working directly on your balcony/terrace and around lounge and bedrooms windows. For your privacy, please keep curtains and blinds closed. To minimise any dust particles going into your property, closing windows could help prevent his, but it's the resident's responsibility and choice in taking in preventative measure.
Very importantly, could you please ensure that all personal belongings i.e. bicycles, plants, garden sets etc. are cleared to allow for works. Please be advised that Equans cannot accept responsibility for any damage or loss of personal items that have not been cleared.
If you have any doubts as to the validity of any identification, please contact the Equans Site Managers, Gary Beasley on 07815 028 625 or Anthony Amayo on 07814 932 726 as soon as possible for guidance or Resident Liaison Officer, Christine Todd on 07766 420 977.
If you have an emergency outside of our normal working hours, you should contact our out of hours emergency number 0333 121 0067 and leave a message stating your name, address and telephone number.
Please contact your RLO, Christine on 07766 420 977 if you have any questions or queries regarding these works and we wish to take this opportunity to apologise in advance for any inconvenience that may be caused.
Our working hours
Meet the Team
-
Phone 0333 121 0067 -
Phone 07815 028 625 Email gary.beasley@equans.com
Site Plan
Documents
-
Resident Newsletters
- Resident Newsletter - Dec 2024 and Jan 2025 (464 KB) (pdf)
- Resident Newsletter_Aug & Sep24 (1.76 MB) (pdf)
- Resident Newsletter_Jun24 (1.65 MB) (pdf)
- Resident Newsletter_Mar24 (2.6 MB) (pdf)
- Resident Newsletter_Nov23 (3.11 MB) (pdf)
- Resident Newsletter_Jun23 (1.76 MB) (pdf)
- Resident Newsletter_NovDec22 (1.83 MB) (pdf)
- Resident Newsletter_Sep22 (2.46 MB) (pdf)
- Resident Newsletter_Jul/Aug22 (1.08 MB) (pdf)
- Resident Newsletter_Mar-Apr22 (989 KB) (pdf)
- Resident Newsletter_Feb22 (627 KB) (pdf)
-
Construction Drawings
- ENG 2020-1168-03D High level plan Seren Park.pdf (1.19 MB) (pdf)
- ENG 2020-1168-04E GA PLAN LHS Seren Park.pdf (1.06 MB) (pdf)
- ENG 2020-1168-02D Mid level plan Seren Park.pdf (1.22 MB) (pdf)
- Cat III Check Sheet for GWCoote (Seren Park - Access Scaffold).pdf (428 KB) (pdf)
- ENG 2020-1168-01E Ground level plan Seren Park.pdf (1.47 MB) (pdf)
- ENG 2020-1168-05E GA PLAN RHS Seren Park.pdf (834 KB) (pdf)
- ENG 2020-1168-07E Sections E,F,G,H Seren Park.pdf (764 KB) (pdf)
- ENG 2020-1168-06D Sections A,B,C,D Seren Park.pdf (719 KB) (pdf)
- ENG 2020-1168-08E Sections K,M,P Seren Park.pdf (908 KB) (pdf)
- ENG 2020-1168-09D Sections T&V Seren Park.pdf (703 KB) (pdf)
- ENG 2020-1168-01 Calcs -Seren Park.pdf (655 KB) (pdf)
-
Proposed Drawings
- 3217-MA-N-DT11-DR-4751-T00.pdf (478 KB) (pdf)
- 3217-MA-N-DT15-DR-4755-T00 .pdf (600 KB) (pdf)
- 3217-MA-N-DT16-DR-4256-T00.pdf (611 KB) (pdf)
- 3217-MA-N-DT17-DR-4757-T00.pdf (599 KB) (pdf)
- 3217-MA-N-DT27-DR-4767-T00.pdf (824 KB) (pdf)
- 3217-MA-N-DT18-DR-4758-T00.pdf (610 KB) (pdf)
- 3217-MA-N-DT28-DR-4768-T00.pdf (680 KB) (pdf)
- 3217-MA-N-DT27-DR-4767-T00.pdf (824 KB) (pdf)
- 3217-MA-N-DT41-DR-4781-T00.pdf (664 KB) (pdf)
- 3217-MA-N-DT46-DR-4786-T00.pdf (855 KB) (pdf)
- 3217-MA-N-DT47-DR-4787-T00.pdf (462 KB) (pdf)
- 3217-MA-N-DT48-DR-4788-T00.pdf (412 KB) (pdf)
- 3217-MA-N-DT49-DR-4789-T00.pdf (418 KB) (pdf)
- 3217-MA-N-EL(E)-DR-2801-T00.pdf (639 KB) (pdf)
- 3217-MA-N-EL(E)-FS-DR-2811-T00.pdf (653 KB) (pdf)
- 3217-MA-N-EL(N)-DR-2800-T00.pdf (644 KB) (pdf)
- 3217-MA-N-EL(N)-FS-DR-2810-T00.pdf (653 KB) (pdf)
- 3217-MA-N-EL(S)-FS-DR-2812-T00.pdf (580 KB) (pdf)
- 3217-MA-N-EL(W)-DR-2803-T00.pdf (715 KB) (pdf)
- 3217-MA-N-EL(W)-FS-DR-2813-T00.pdf (701 KB) (pdf)
- 3217-MA-N-EL-DR-2820-T00.pdf (332 KB) (pdf)
- 3217-MA-N-SL-DR-0200.pdf (486 KB) (pdf)
- 3217-MA-N-EL(S)-DR-2802-T00.pdf (597 KB) (pdf)
-
Letters
- Site Compound removal and completion of works - Jan 2025 (100 KB) (pdf)
- Broken balcony balustrade glass panel_May24 (143 KB) (pdf)
- Scaffold strike_Section 2 and corner of Section 6_Oct23 (120 KB) (pdf)
- Zinc stripping 24 - 25 Seren Park_Oct23 (121 KB) (pdf)
- Zinc Stripping and Installation 188_Oct23 (122 KB) (pdf)
- Balcony Zinc Cappings 31-62_Oct23 (127 KB) (pdf)
- Balcony Zinc Cappings_113-148_Oct23 (127 KB) (pdf)
- Update on Works Letter_Sep23 (94.9 KB) (pdf)
- Update on Works Letter_Aug23 (94.5 KB) (pdf)
- Balcony Zinc Cappings_Jun23 (126 KB) (pdf)
- Commencing Zinc stripping_Jun23 (121 KB) (pdf)
- Zinc cappings installation to balconies_Jun23 (126 KB) (pdf)
- Dismantling hoist and relocating from Section 2 to Section 3_Feb23 (156 KB) (pdf)
- Scaffolding erection inset balconies_Section 5 & 6_Jan23 (152 KB) (pdf)
- Section 1 - Dismantling hoist and relocating to corner of section 4_Jan23 (124 KB) (pdf)
- Section 6 - Render and cladding removal and balcony clearance_Jan23 (131 KB) (pdf)
- Recomencing Zinc stripping_Jun23 (121 KB) (pdf)
- Section 5 part of B2 C1 B1 A1 - render and cladding removal and balcony clearance_Oct22 (132 KB) (pdf)
- Zinc stripping on Section 5 and Section 6_Mar23 (120 KB) (pdf)
- Scaffold strike letter Section 2 Levels 9 and 8_Mar23 (122 KB) (pdf)
- External Works_SectionA1_Entrance Exit Door Temporary Closure Safety Letter_Jun22 (142 KB) (pdf)
- Temporary no access vehicle entrance exit to underground car park_Jun22 (147 KB) (pdf)
- Balcony Scaffolding and Balcony Clearance Section 6GB_Oct22 (151 KB) (pdf)
- Render Cladding Removal Reminder_Jun22 (368 KB) (pdf)
- Balcony Scaffolding Works Letter_Jun22 (145 KB) (pdf)
- Cladding removal and balcony clearance_Aug22 (128 KB) (pdf)
- Fire Drill Practice_EQUANS Staff Only_Jul22 (353 KB) (pdf)
- Ground Floor Balcony Clearance Letter_May22 (145 KB) (pdf)
- 1st Floor Residents - Restricted Access Flats 1 & 2 Balconies Patios Letter_Jun22 (150 KB) (pdf)
- Render Cladding Removal Block C1 and part section B2 Letter_Jun22 (368 KB) (pdf)
- Roof Level works Letter_Jun22 (143 KB) (pdf)
- Block C1 Balcony Scaffolding Letter_May22 (259 KB) (pdf)
- Roof Level Works Letter_May22 (145 KB) (pdf)
- Draught Podium Works Letter_May22 (145 KB) (pdf)
- Completion programme - update 16.12.24 (450 KB) (pdf)
- Completion Programme_13.05.24 (638 KB) (pdf)
- Halloween Activity Pack (990 KB) (pdf)
- Site Team Change Flyer_May22 (875 KB) (pdf)
- Seren Park Resident Information Pack_May22 (9.25 MB) (pdf)
- Summer Activity Pack (1.63 MB) (pdf)
Photos
Phase of Works - Milestones
-
Phase 1
Seren Park - Cladding Replacement has finished this stageSite set up. Erecting hoarding to the welfare area situated at the bottom of Restell Close. Installing temporary services, water and electric. Delivery and siting of welfare containers, offices, toilets, storage containers etc.,
Carrying out various surveys on site to enable the working designs for the new cladding, Off-site works, preparing drawings for cladding including commencement of fabrication for these items.
-
Phase 2
Seren Park - Cladding Replacement has finished this stageScaffold erection to blocks A1 & A2
-
Phase 3
Seren Park - Cladding Replacement is currently at this stageMain works commence, removal and reinstatement of external cladding and balcony refurbishments.
-
Phase 4
this is an upcoming stage for Seren Park - Cladding ReplacementWorks completing. Scaffold strike completing, remedial works to podium hard landscaping, demobilisation of site set up and site clearance.