Iveagh House


Welcome to the microsite for Iveagh House. Equans is undertaking works on behalf of The Guinness Partnership.

This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Works on this scheme include roof renewals, external brick & concrete repairs, windows, balcony works, sprinklers and M&E installation.

The project began in the first quarter of 2023, and is due to complete in 18 months.

This website will keep everyone updated on the progress of the scheme - and if you have any questions, please refer to the contact us section.






Welcome to the microsite for Iveagh House. Equans is undertaking works on behalf of The Guinness Partnership.

This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Works on this scheme include roof renewals, external brick & concrete repairs, windows, balcony works, sprinklers and M&E installation.

The project began in the first quarter of 2023, and is due to complete in 18 months.

This website will keep everyone updated on the progress of the scheme - and if you have any questions, please refer to the contact us section.





  • An update on our works - February 2024

    Welcome to our latest works update for Iveagh House.

    These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.


    It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.

    Our progress throughout February:

    • Works have started on the annexe building roof replacement and are currently 75% complete
    • Works are ongoing to the new veranda balconies
    • Window concrete surrounds on the annexe building are ongoing
    • Automatic opening vents (AOVs) to north, centre and south stairwells are ongoing
    • Communal electrical works are ongoing
    • Communal fire detection system are ongoing
    • We are approximately 90-95% complete on the concrete and brickwork repairs
    • We are approximately 85% complete on the balconies (full size and juliet's)
    • All HIU cupboards on all floors have been built however decorative works to the corridors will be done separately

    Important information:

    The Equans RLO, Ayo and Guinness Customer Liaison Officer are available at the Community Hall, Monday to Friday during the following hours: 8am-12pm and 2pm-5pm. They are available to visit and have face-to-face conversations.

  • Resident updates from Guinness Partnership

    Resident updates from Guinness Partnership are now available within our Document Library.


    If you have any queries or concerns about the works being undertaken and would like to speak to Guinness Partnership directly please call them on 0303 123 1890 or via email at Plannedwork.IveaghHse@guinness.org.uk

  • Site team changes

    We'd like to make you aware of some recent changes to your Equans site team.

    Sadly we've had to say goodbye to Site Manager, Adam Melpous as he has now left to join another project. As his replacement we've recently welcomed Senior Site Managers, John Hollington and Paul Edwards.

    Although contact details for both John and Paul can be found within the 'Contact Us' section on the homepage, we'd like to remind you that any questions, queries or concerns you may have about the works being undertaken should be reported to your appointed Resident Liaison Officer, Ayo as your first point of contact.

    Please join us in welcoming John and Paul to the Iveagh House project.

  • An update on our works - January 2024

    Welcome to our latest works update for Iveagh House.

    These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.


    It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.

    Our progress to date:

    Throughout January we started the following works:

    • Installation of new juliet balconies
    • External brickwork/concrete repairs to the main block and the annex
    • External rendering
    • Internal remedial works to various properties
    • Installation of new HIU cupboards within communal areas
    • Internal heating renewal works
    • Installation of new kitchen fans

    Upcoming works throughout February:

    • Installation of new balcony terrace floor coverings
    • Installation of AOVs (Automatic Opening Vents) to communal areas
    • Installation of new roof coverings to the annex

    Important information:

    The Equans RLO, Ayo and Guinness Customer Officer are available at the Community Hall, Monday to Friday during the following hours: 10am-12pm and 2pm-4pm. They are available to visit and have face-to-face conversations.

  • An update on our works - December 2023

    Welcome to your first works update - this is where we will regularly update you on our progress with the works being undertaken at Iveagh House.

    These updates are provided by members of the site team and are always as up to date as possible, however If you have any queries, questions or concerns about the works please contact your appointed Resident Liaison Officer (RLO), Ayo Adagunodo on 07890 630 331.


    It is our intention to provide a regular update to the residents at Iveagh House as to what works have taken place and what works are upcoming.

    Our progress to date:

    Throughout December we started the following works:

    • External brickwork/concrete repairs
    • External balcony floor coatings
    • Internal remedial works to various properties
    • Installation of new HIU cupboards within communal areas

    Upcoming works throughout January:

    • Installation of new kitchen fans
    • Installation of new Juliet balconies
    • Automatic Opening Vents (AOVs) to communal areas

    Important information:

    The Equans RLO, Ayo and Guinness Customer Officer are available at the Community Hall, Monday to Friday during the following hours: 10am-12pm and 2pm-4pm. They are available to visit and have face-to-face conversations.

  • Hello, greetings and welcome

    On behalf of the Equans site team delivering these works, welcome to the Iveagh House resident website.

    On this site, we will display important information about the scheme including an introduction to Equans, our expertise and the team working on this scheme. We will also provide you with key contact details including our emergency out of hours number, show progress photos and provide updates on the works we're delivering throughout the duration of the scheme.

    Take your time to browse each section at your own leisure but as a summary please see below:

    • Introduction: Found at the top of the left side of the page, this section is our introduction to you, providing a brief explanation of who we are and what works we'll be carrying out on this scheme.
    • News Feed: Found on the left side of the page underneath the 'Introduction' section, the 'News Feed' includes all our recent news and activity. It's in date order so the most recent news is always at the top for your convenience
    • Contact us: Found at the top of the right side, this section details every member of the Equans site team appointed to this scheme as well as a brief explanation of their role and most importantly their contact details. We've shown the key contacts on the main page, but click more to see the full team
    • About Equans: This section tells you a little more about us, our expertise and our approach to corporate responsibility.
    • Careers at Equans: We're keen to promote recruitment, click the image displayed to view all our current vacancies. We also have apprenticeships available - just contact us for more details!
    • Document Library: Like it says on the tin, here is where we display any relevant documents related to the works - you may already have a paper version of these documents, so these are just a copy that may come in handy to view, download or print
    • Photo Library: Like the 'Document library', this is where we will display our progress photos taken throughout the duration of the works. Each image will also have a short caption to explain what's being shown

    Please take the time to familiarise yourself with the website if you have any queries or concerns about works we're undertaking don't hesitate to call your dedicated Resident Liaison Officer - details can be found within our 'Contact Us' section.

  • We're closing for the festive holidays!

    We would like to inform you that our Iveagh House site will be shutting for the festive holiday from Friday 22nd December and re-opening on Tuesday 2nd January 2024.

    In the event of an emergency during this period, please continue to use our dedicated out of hours number - 0800 328 7244.

    From everyone in the Iveagh House site team, we hope you enjoy the festive break.


  • Site team achieve 'Excellent' rating from Considerate Constructors Scheme

    The team at Iveagh House have successfully achieved an impressive score of 43/45 from their recent audit visit by the Considerate Constructors Scheme (CCS) earning them an 'Excellent' rating.

    When the CCS monitor visited the scheme at the end of November to carry out their audit of the site, they commented things like "Overall, the site demonstrates excellent practices and performance across the checklist to meet the Code of Considerate Practice throughout the works. The team has established and maintained a good relationship with their local community and they are tracking well against sustainability and social value targets."

    The CCS is an independent organisation founded to raise standards in the construction industry to ensure all construction sites present an image of competent management, efficiency, awareness of environmental issues and above all neighbourliness. Monitors from the scheme regularly audit our sites to ensure we are adhering to the scheme’s Code of Considerate Practice which is designed to encourage best practice beyond statutory requirement.

    Each audit is split into three categories; respect for the community, protecting the environment and valuing the workforce each with a potential score out of 15 with a total combined max score of 45 available. To score above 13 in any category warrants an excellent level of achievement for that category.

    Congratulations to Site Managers, Adam Melpous and Adam Holman and the rest of the site team, who work so hard every day to maintain such high standards

  • Happy Halloween from Equans

    From all of us at Equans, we wish you a happy Halloween.


    A children's activity pack can be collected from your Resident Liaison Officer. Alternatively this can be viewed and downloaded from our 'Documents Library'.

    Please be careful if carving pumpkins and stay safe whilst trick or treating.

Page published: 20 Dec 2024, 09:32 AM